Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Monthly CCR project meeting. • Discussed with Ramos additional wall space needed for pool bunker control panels and electrical service panel. • Scheduled Randell the wall paper hanger to review powder room wall for tomorrow Friday. • Site visit from Drew and Marc with Locale. • Site visit from Marc T. • Began wood bleaching of the fading roof top ipa decking. • Ramos pools onsite setting equipment at bunker room. • Hilltop on-site. • Woodys on-site setting toilets at Kona and Haleakala. • Ford on site. • Set kegerator at lower storage room. • Received notice from Next Level the island slab fabrication is delayed and headed for round 3 due do machinery malfunctions. • Completed HES interior punch list for all things electric. • Received notice we are now in HECOs system for permanent power approval. • Continued fabricating concrete steps for spiral stair case. Quote of the day: “Third island is the charm!!”
|
|||||||||||||||||