Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 10/9 & 10/10 • Aloha Friday • CMAC on-site. • CMAC continuing drench excavations from house to street. • Reviewed sewer connection location with CMAC. • Prepped tub drain connections for Woodys Plumbing. • Met with drywall contractor, scheduled finishers returning next week. • Prepped main lanai, site, house and pool for crew appreciation party. • Assisted in set up of crew appreciation party. • Received and passed Reynolds hydro inspection at acrylic to pool shell silicone connection. • Darren/Next Level on-site measuring for slab counter tops throughout. • Completed Haleakala bed and head wall assembly install. • Began Kona bed assembly prep and install. • Site meeting with Mike R. to review all areas ready for finish set. • Began baseboard installs at lower level. • Hill top prepping lower back lanai for tile installs. • Hilltop on-site continuing on tile and grouting installs throughout. • Supplied Monkey Pod slab material list for drying. • Installed access panel at back of urinal. • Worked with Keith Drew on the layout of the interior stairs. • Attended crew appreciation pool party! Mahalo Mike! Quote of the day: “Appreciation is a wonderful thing. It makes what is excellent in others belong to us as well”
|
|||||||||||||||||