Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Site meeting with Kerry Kamalii from HI Gas. • Woodys plumbing on-site hooking up BBQ gas , commissioning hot water system. • Worked with Keith Drew laying out upper landing at elevator stairs. • Signature Shades on-site. • Contacted Darren in regard to counter top slab work remaining. • Reviewed gas termination at propane tank with Woodys plumbing. • Reviewed tiki torch control timer, and configuration. • Received shop drawings for the interior glass railing. • Completed verifying said shop drawings. • Spoke with Marc Taron about the WCA Thursday 11:00 meeting. • Tomas Landscape crew on-site setting sprinkler irrigations. • Installed Haleakala pocket door handle. • Mike B. and Tygrr working on shower bench supports. • Completed dura rock fabrication for the cantilever stairs. • HES on-site. • EDesign on-site. • Confirmed Sturdevant will be back on site tomorrow Thursday to repair FCU pan at rack room, and begin commissioning AC systems. • Received site visit from Mark Cruz and client. • Received estimate from Hammerhead Aquatics for the cosmetic acrylic bead install. Quote of the day: “When people talk, listen completely”
|
|||||||||||||||||