Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Reviewed BBQ area details with signature shades Daren and Dimitri. • Reviewed all remaining countertop areas with Darren. • Sturdevant on-site commissioning AC systems. • Tomas Landscape crew setting sprinkler system. • Scheduled meeting with Casey Lamb for tomorrow morning 10:00 AM do review property line impacts a gulch. • Worked with Signature shades on master trellis layout. • Hilltop back on-site prepping for pool tile installs. • Confirmed final shop drawings for interior stair glass railings. • Weekly project accounting meeting with Gen. • Began completion of Parklex soffit at elevator stairs. • Keith Drew on-site performing various welding. • Keith Drew connecting pool stairs for pool bonding. • Ramos pools on site setting blue tile at pool window, and swim lane entrance. • Worked with HES on various electrical details. Quote of the day: “Play big. Start where you are. Use what you have. Do what you can.”
|
|||||||||||||||||