Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Worked on project allowances, change orders, accounting. • Dropped off project invoices to CCR counting office. • Site meeting with owner of Interior Environments Dave Brzusek. • Drywall install at observatory and rack room complete. • Drywall finish at observatory and rack room beginning. • Began install of electrical devices at observatory and rack room in preparation of electrical rough in inspection. • Laid out and began prepping for install of master outside shower, shower tower. • Continued Monkey Pod milling. • Continued install of roof top decking. • Lake Lowe is now officially closed due to continued drought conditions. • Received approved for additional concrete samples. Quote of the day: “The past is prologue”
|
|||||||||||||||||