Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:

• Worked on project allowances, change orders, accounting.

• Dropped off project invoices to CCR counting office.

• Site meeting with owner of Interior Environments Dave Brzusek.

• Drywall install at observatory and rack room complete.

• Drywall finish at observatory and rack room beginning.

• Began install of electrical devices at observatory and rack room in preparation of electrical rough in inspection.

• Laid out and began prepping for install of master outside shower, shower tower.

• Continued Monkey Pod milling.

• Continued install of roof top decking.

• Lake Lowe is now officially closed due to continued drought  conditions.

• Received approved for additional concrete samples.

Quote of the day:

“The past is prologue” 



Sent with Basecamp You can reply to this email or respond in Basecamp.
This message was sent to Alana Scott, Artie Ferreira, Bob Polasek Jr., Cody Macdonald, Don Kimball, Drew Kauffman, Genevieve Sison-Dollopac, Ikaika Reyes, John Rawson, Joshua Cardeno, Kelcey Sykes, Kristen Totah, Lovely Pascual, Marc Taron, Marlon Silloriquez, Marsha Kaleikau, Mati Stamatiou, Matt Hecox, Michelle Leatherman, Mike Bennett, Nick Ross, Roger Cabudol, and Sarah Marshall.
UnsubscribeChange your notification settings
Get the Basecamp app for iPhone or Android!
Download on the App Store Download on the Play Store
2ad5a8df71a69d3515c1642d
Reply all
Reply to author
Forward
0 new messages