Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 1/12. 1/13. 1/14. • Developed island glass bar top details with Mike B. • Worked with Drew on spiral to roof stair details. • Weekly project meeting with Gen. • Ordered cut mirrors from Glass Products Hawai’i. • Fabricated and installed Mahogany mirror frame at pool bath. • Installed aluminum desk post supports at Mauka and Kihei bedrooms. • CMAC delivering Bioretention soil mix for basin back fills. • CMAC schedule to back fill basins Friday. • Site meeting with Dimitri. • Hilltop tile setters onsite. • EDesign not on-site all three days. • HES electric on-site. • Keith Drew crew on-site working on spirals to roof. • Located Toto remote Smurf's at Hale and Kona bath walls. • Updated Jon’s interior punch list. • Completed roof top furniture fabrications. • Contacted Maui Plumbing to schedule Finnish sets. • Scheduled site meeting with Leo for tomorrow to review concrete slab placement at Bunker room. • Received Ferguson quote from Gen for replacement sink and soap dispensers. • Worked with Joel at Ferguson regarding 24” sub zero door panel and for to door connector kit order. • Completed first phase of Monkey Pod stair tread milling. • Picked up cement, cement colors for Sandstone stair tread and pool coping samples. • Received site visit from Mike B. and friends. • Woodys plumbing on site. • Completed install of stackable washer and Dryer at master Walk in closet. • Completed install of refrigerator and microwave drawer at lower kitchenette. • Scheduled off haul of CCRs scissor lift for tomorrow AM. • Removed interior doors 228 and 219 to return to Island Wood Door for repair. Quote of the day: “Grey days are not empty-they are just full of pause”
|
|||||||||||||||||