Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Completed mock ups for tomorrow’s Locale meeting. • Ramos bros continuing install of pool equipment at bunker room. • Continued fabrication of concrete steps at spiral to roof stairs. • Completed clean out of back yard. • Continued site material consolidation for off haul. • Contacted wall paper hangers. • Received notification the the replacement sink for the pass through bar has arrived at Fergusion. • Received notification the first shipment of furniture arrives to the site on March 16th. • Worked with Mike B. on various electrical finish details. • Hilltop continuing working on tile installs at elevator shaft exterior, and half wall at outside master shower. • Weekly OC project meeting with Mike B. • Ford onsite. • Donny on site applying final top coat at kegerator pad. • Edesign not on-site all week. • Elegant painting on-site painting stair well. • Keith Drew on-site. • Began laying out elevator planter box. Quote of the day: “Details matter. It’s worth waiting to get it right”
|
|||||||||||||||||