Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Received delivery of Signature Shades “Struxure” unit for roof top. • Woodys plumbing on-site removing test balls at sewer line • Received and passed Maui County Plumbing sewer line inspection. • CMAC onsite tomorrow to begin first stage of backfill at utility trench. • Woodys plumbing on-site Monday to install gas and water lines. • Began working back on roof top furniture. • Completed details of access panel at back of urinal. • Completed install of Iron Away at upper level laundry room. • Approved Elegant Paintings proposal to paint the drywall ceilings. • Completed wood ceiling mock up for Elegant painting clear coat samples. • Hilltop working on exterior shower floor tile installs. • Site meeting with Mike Ramos. • Continued base and door Fry Riglet installs at lower level. • Keith Drew and crew continued install of steel stingers for the interior stairs. • Drywall finishers continuing at main level. • Installed Edesigns shade box at WIC. • Continued covering and protecting floors and cabinetry. • Continued setting cabinet toe kicks. • Site meeting with Darren, Darren dropped off custom sink prototype. Quote of the day: “It’s easy to judge. It’s more difficult to understand”
|
|||||||||||||||||