Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Aloha Friday!! • Spoke with landscape contractor Tomas about a next week site meeting. • Requested site meeting availability from Bryan Maxwell. • Site meeting with Mike B. • Keith Drew on-site working on completion of the spiral stairs to roof top. • Spiral stairs to roof top are now usable. • Continued working on roof top decking installs. • Drywall crew on-site completing drywall install at observatory and observatory bathroom. • Drywall crew back Monday for rack room drywall install. • Relayed grout color selection for master wall tile to Hilltop. • Hilltop one man crew on-site. • EDesign one man crew on-site. • HES one man crew on-site. • Provided Donny with bunker room slab square footage. • Received ETA of first week of March for the remaining exterior door order from Source. • Continued milling of the Monkey Pod stair landings. • Reviewed closet rod details with EDesign. EDesign provided prototype for Mike B. to review. • Worked with Mario on lower entry bench details. • Performed clean up. • Dropped off coded invoices. Quote of the day: “A steady mind outlast a sharp one”
|
|||||||||||||||||