Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• Staged delivery of the Struxure Shade unit for the BBQ area. • Reviewed the glass railing stand off layout and detail for the Monkey Pod stairs. • Received and reviewed layout of the glass railing clips for the back donut hole. • MTZ Landscapes completing gas line excavations for the front tiki torches. • Scheduled MTZ dump truck for rubbish removal. • Woodys plumbing scheduled for tiki torch gas line installs for Monday 5/11. • Completing install of the big garage work bench. • Continued prepping for the steel stair installs. • Received confirmation the Hilti concrete connection bolt order due to arrive Friday. • Laid out pool water fall columns for construction. • Ramos pools onsite. • Hilltop on-site. • Mike B. and Tygrr continuing on outside shower gate fabrications. • Continued boring drain line hole at back lanai area. • HES Kamalu pulling wire for install of the pool sub panel. • Continued prepping and sealing roof top decking. • Received approval for 30” back culvert CMAC scope. • Built up inverted roof line radius at elevator area. • Scheduled pre con meeting for Thursday 5/7. • Nahem onsite. • EDesign not on-site. Quote of the day: “The secret of staying young is to live honestly, eat slowly, and lie about your age”
|
|||||||||||||||||