Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Received delivery of the upper entry way sculpture. • Sturdevant on-site completing commissioning of AC system minus thermostat function. • Mike B. on-site working with Sturdevant on thermostat issues. • Completed roof top elevator switch box. • Ramos pools onsite installing roof top solar pool panels. • Began fabrication of main kitchen recycle shoots/cabinet. • Keith Drew continuing work on circular stair stringer. • Site Meeting with Dimitri. • Received notice from Hawai’i Glass products the side door elevator glass and dounut hole railing glass has arrived, scheduling CCR pick up. • Billy Wilson Drywall onsite onsite doing final drywall touch ups. • Scheduled Elegant Painting to perform final painting starting Monday. • Performed interior electrical walkthrough with Mike B. and HES. • Tomas Landscaping on-site delivering top soil, and installing sprinklers. • Wolf warming drawer scheduled for a Monday delivery. • Floor and coping tile landed, waiting for site delivery schedule. • Nahem on site. • EDesign on site. Quote of the day: “No is a complete sentence”
|
|||||||||||||||||