Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Aloha Friday!! • CMAC delivered the organic compost for the bioretention basin back fill mix. • CMAC now scheduled for Tuesday back fill. • Off loaded first delivery of furniture into small garage with Mike B. and crew. • Site meeting with Mike B. • Began concrete coping and stair color samples. • Hilltop on-site. • Keith Drew on-site. • One man Edesign on site half day. • HES electrical onsite. • Woodys plumbing on-site. • Began install of vase puck lights. • Began layout and install of outside master shower tower. • Performed clean up. Quote of the day: “Every Friday is a reminder that life is about balance”
|
|||||||||||||||||