Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Continued sub top installs at BBQ. • Reviewed Traeger space at BBQ with Mike B. Mike to look into clearances. • Reviewed Island Glass bar top dimensions with Mike B. Mike to follow up. • Laid out shower heads to be tested with Mike B. • Keith Drew on site continuing on spiral stair case to roof. • Site meeting with John/Island Wood Door. Reviewed warranty repairs to doors 228, 219. John to verify schedule for repairs. • Began back on roof top decking installs. • Began working on mirror order. • Requested mirror frame material for pool bath from Kristen. • EDesign on-site. • Hilltop on-site. • HES PV on- site. • Received tracking information from Tile Tech for the roof top decking shipment. • Received Signature Shade delivery. • Continued first phase of milling Monkey Pod treads for interior stairs. Quote of the day: “A ship is always referred to as ‘she’ because it cost so much to keep one in paint and powder”
|
|||||||||||||||||