Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 2/12 & 2/13 • Aloha Friday!! • Sturdevant on-site setting finishes at interior, setting condensers at roof top. • Worked with Mike B. various details. • Mike B. completing HECO Elect. service application. • Mario and team onsite. • Ford onsite. • Hilltop on-site completing tile replacement at observatory window, and basalt power washing. • Keith Drew on-site setting railing cables at spiral stairs to roof. • Continued roof top decking install. • Continued form fabrications for spiral stairs to roof concrete treads. • EDesign on-site delivering TVs and equit. • Completed drilling holes in interior steel stair structure for edesigns light wire routes. • Continued prepping elevator for tile installs. • Site meeting with landscape contractor Tomas and Mike B. • Worked with Next Level on kitchen island details. • Next Level to complete kit island by next weeks end. • Access Lifts on-site. • Site will be closed Monday in observance of Presidents Day. Quote of the day: “Friday makes Monday worth it”
|
|||||||||||||||||