Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC:
• CMAC on-site. • CMAC continuing drench excavations from house. • Laid out sewer, gas, water terminations for CMAC. • Site meeting with Woodys plumbing to review French excavations and tub sets. • Topped off pool at 33,000 gallons total. • Spoke with Jason/Reynolds, Jason to perform Acrylic/Silicone inspection tomorrow 8:00 AM. • On site meeting with Darren review and measure all slab counter tops. • Completed installing lower level entertainment center at living room. • Continued Haleakala bed assembly install. • Received notice from Josh and Mike R. that the replacement smart-glass will be arriving onsite Tuesday next week. • Completed baseboard installs at main level. • Site meeting with Mike B. • Site meeting with Dimitri. • Laid out concrete cut at lower back lanai. • Hilltop on-site continuing on tile installs throughout. • Scheduled Monkey Pod slab material meeting tomorrow 10:00 AM. • Received delivery for the Signature Shade retractable awning for the main lanai roof. • Worked with Keith Drew on the layout of the interior stairs. • Keith picking up interior stair stringer material from the harbor today. Quote of the day: “The harder I work the more luck I have”
|
|||||||||||||||||