Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Scheduled site meeting with Mike Ramos. • Spoke with Loren Osborn regarding HES. • Received notification the cargo lift is on island, awaiting delivery schedule. • Received confirmation from Access Lifts they will be on-site next week to begin install of the cargo lift. • CMAC completing install of the front site drain lines to termination area. • Continued bed assembly install at Makai bedroom. • Continued base board installs at lower level. • Confirmed all drywall ceiling's are paint ready. • Scheduling Elegant Painting to complete paint at all drywall ceilings. • Site Meeting with Josh/Edesign. EDesign to begin installs week of 11/3. • Hilltop completing tile installs at main level shells reef entry wall, and lower back lanai floor tile. • Hilltop working on exterior shower floor tile installs. • Spoke with Darren at Next Level Granite. Darren to begin countertop installs end of this week. • Completed all base and door Fry Riglet installs at main level. • Drywall finishers continuing at main level. Quote of the day: “Outer order contributes to inner calm”
|
|||||||||||||||||