Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Leo’s concrete on-site prepping pool bunker slab. • Pool bunker slab scheduled for concrete placement tomorrow Thursday 10:30 AM. • Added two additional auxiliary conduits under bunker slab to exterior. • Weekly project meeting with Gen. • OC meeting with Gen and Mike B. • Ramos pools onsite detailing pool shell corners. • EDesign on-site. • Hilltop on-site. • Keith Drew not on site. • HES elect on-site continuing to hook up edesigns transformers and drivers etc throughout. • Installed HES PV emergency PV shut off at electrical room closet. • Loaded IPE decking on roof. • Began back on IPE decking installs at roof top. • Site meeting with Mario to review receptacle move at lower living entry bench area. • Next Level on-site completing slab installs at master tub deck and counter top at lower dumb waiter space at storage room. • Reviewed shelf details with Next Level at Kona Bath tub. • Began prepping for support off Kona bath tub shelf. • Met with Chuck with Maui Plumbing Fire. MPF to schedule interior finish fire sprinkler head sets sometime next week. • Approved Woodys plumbing progress invoice. • Scheduled Woodys Plumbing to return next week Wed. Thur. & Fri. • Received water filtration system from Mike B. • Reviewed bunker room sink, faucet and accessories. • Met with drywall contractor Billy Wilson, Billy to have observatory and rack room drywalled this week Friday. • Began milling monkey pod landings. • Received notice from Gen that the two Mt. Plumbing replacement soap dispenser parts arrived at Fergusion Plumbing. Quote of the day: “Every closed gate hides a key called persistence”
|
|||||||||||||||||