Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: • Site meeting with Tomas. • Tomas crew on-site setting landscape sleeves across lower driveway. • Laid out driveway for CMAC. • CMAC on-site delivering and installing structural driveway gravel base. • FaceTime meeting with Mike Ramos and acrylic silicone contractor to discuss final details at pool tile to silicone/acrylic • Ramos completed spa tile and grout install. • Ramos began install of waterline tile. • Ramos began detailing infinity edge for tile install. • Keith Drew on-site working on circular stair stringer at elevator. • OAC meeting, stairs, elevator glass. • Began conditioning the wood ceiling speaker grills. • Completed observatory desk/cabinet installs. • Began Re screening Fleetwood screen doors. • Installed remaining glass clip at donut hole. • HES on-site. • Completed underground utility conduit hook ups At street. • Received notice the additional Italian porcelain floor tile is to arrive on Maui 6/14. • Mike B. & Tygrr on-site. Quote of the day: “Live Aloha”
|
|||||||||||||||||