Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: On site: • HES • Hilltop Tile • Ramos Pools • Nahem • EDesign • Tomas Landscapes • Jake the plumber • Cleaning crew • Keith Drew • CCR Crew Scopes performed: • HES trouble shooting and finishing interior electric throughout. • Hilltop continuing on shells reef tile install at wet suit shower. Began back splash tile install at outside observatory bar. Continued tile reinstall at makai stairs. Completed shells ref tile install at rec room round window. • Ramos pools began pool waterproofing process. • Nahem working with Jake the plumber on kegerator install at both levels. • EDesign working at rack room up loading Wi fi terminals and speaker operations. • Tomas landscaping prepping for drive way concrete install at round about. Met with Mike B. to pick out concrete stamp pattern. Tomas secured chosen stamp, awaiting color choice. Sent Drew and Mike B. concrete colors Hawaiian Cement carries. • Cleaning crew completed first pass cleaning at both interior levels. • Keith Drew completed welding of uprights at elevator circular stairs and began fabrication tread templets. • CCR crew participated and assisted in house prep and set up at interior. Site organization and safety precaution installs. Install of back yard railing Post, priming back yard railing post for paint. Cable lay out and began drilling of post. Mounting equipment for Nahem, helping Mike B at interior. • Weekly project meeting with Gen. • Dropped off coded project receipt's at CCR. Quote of the day: “Put the right person in the right role, and the job becomes an opportunity—not a burden.”
|
|||||||||||||||||