Jon Lowe, Super / Project Manager at Castaway Construction & Restoration LLC: 2/5 & 2/6 • Aloha Friday! • Woodys plumbing on-site installing solar hot water system. • HES on site wrapping up device installs throughout. • Received notice from HES the HECO permanent electrical service has been ordered. • Mario and team delivering and installing monkey pod shelf at Hale bath, and lower entry nook bench. • Began additional mirror installs at master bathroom. • Continued concrete coping samples. • Drywall finishers onsite. • Set up Ford in small garage to begin his art work piece. • EDesign on site. • Strudavant Scheduled to return 2/12 to set interior grills, T Stats, and roof top condensers. • Site meeting with Landscape contractor Tomas and Mike B. • Keith Drew not on site, rained out. • Contacted Maui Garage Door about rec room camera. • Maui Plumbing on-site. • Hilltop on-site. Quote of the day: “ Tomorrow is built quietly out of today”
|
|||||||||||||||||