Group: http://groups.google.com/group/gulmohar-garden-svp/topics
- Meeting With Lawyer on Saturday 14 July, 2012 At 2:30 pm At Mohan Nagar Mandir [2 Updates]
- Listing of grievances against SVP Builders [1 Update]
Varun Goel <vgoe...@gmail.com> Jul 09 01:32PM +0530
Hi All,
Some of us having problem for the meeting with Lawyer on Tuesday, So I have
fixed a meeting with lawyer Mr. Brahmdev Tyagi on coming Saturday i.e. July
14, 2012 at 2:30 pm at Mohan Nagar ...more
"govind ballabh joshi" <govi...@rediffmail.com> Jul 09 01:09PM
Dear Vinish,
I will be there
Regards
Govind ballabh
On Mon, 09 Jul 2012 13:32:31 +0530 wrote
>Hi All,
Some of us having problem for the meeting with Lawyer on Tuesday, So I have fixed a ...more
Varun Goel <vgoe...@gmail.com> Jul 09 01:03PM +0530
Hi All,
I am herewith attaching the Grievance Summary for your convenience. You
have to give this summary to the lawyer so that he can mention all the
points in the legal notice which will go to ...more
You received this message because you are subscribed to the Google Group gulmohar-garden-svp.
You can post via email.
To unsubscribe from this group, send an empty message.
For more options, visit this group.
Hi friends,
Currently I am in mumbai and ready to contribute my share for leagle procedures as and when required.
Regards
Utful Kr. Tyagi
Hi all,
Please share all your thoughts in other Google group for which Vinish has already sent invitation. Please join it and also see latest site pics.
Regards,
Stanly
You received this message because you are subscribed to the Google Group gulmohar-garden-svp.
You can post via email.
To unsubscribe from this group, send an empty message.
For more options, visit this group.
--
Regards,
Anil Kumar GuptaB. Tech, ISTQB, ITIL, MCSE, ISO 9001:2000----------------------------------------------------------------------------------Lead auditor for ISO 9001: 2000 QMS,Certified Testing Professional - International Software Testing Qualification BoardAuthor - Quality Assurance for Dynamics AX based ERP solution' (ISBN: 1847192912)Author - 'Software Testing : Understand Plan and Execute' (ISBN: 1847193452) (Under publications)Associate Member - Global Association of Billionaires and MillionairesMember - PMIHonorary Member of Advisory Board - QA Guild
Chief Coordinator - Indian Engineers Forum (Riyadh)Skype: "sqaguru"
MSN: "sqaguru"
19th July, 2012
M/s. SVP Builders (I) Ltd.,
17, Kiran Enclave
Main G.T. Road
Ghaziabad – 201 001
Sub: Shortcomings observed in Flats (Flat T- IV - 406)
Ref: Your letter No. SVP/GD/12-13/PL/T-IV-406 dated 9th July, 2012
Dear Sirs,
I am in receipt of your letter referred above.
In this context, I would like to bring to your kind notice that I had visited the site of flat and it has been observed that the flat is not yet ready for taking possession. The shortcomings observed are given below:-
1. A copy of the completion certificate may be provided to me for enabling me to take possession.
2. There is no provision for electricity connection now. Without electricity connection from U.P. Electricity Board, it will not be possible for me to occupy the flat.
3. There is no link road in the premises of the flats. Without completion of the roads, it will not be possible to occupy the flat.
4. There is no parking space now. Without providing parking space, it will not be possible to occupy the flat. You have not mentioned any alternative parking after occupying the flat.
5. You have not informed me the final super area of my flat till now as per terms & conditions of allotment of Flat F IV 406 mentioned at sl. No. 2 (a) .
6. The registration of the flat may be done after finishing the complete job before taking possession of the flat and after getting the completion certificate from GDA and other certificates from concerned Agencies, wherever required.
7. The material used for construction and other fittings provided in the flat are of poor quality and not as per the brochure.
8. Copies of all inspection reports from concerned Authorities may be provided.
You may take immediate action and confirm the action taken for removal of the shortcomings mentioned above for enabling me to take possession of my flat.
Thanking you and awaiting your early response,
Yours faithfully,
( Anil Sharma )