Spuyten Duyvil Project Update No. 03 (week ending May 26, 2018):
Good afternoon, everyone.
Attached is an updated schedule with all relevant and new information shown. In this update, you’ll notice we are maintaining schedule for the first North channel closure to begin on Monday, June 11, 2018. On this day, we will mobilize the Left Coast Lifter (LCL) onsite and anticipate the removal work to begin during the early/ middle part of that same week. Our goal is to have the North channel reopened by the end of the week so there are no impacts to the waterway events scheduled for that weekend. As we get closer to this work, more frequent updates will be shared to provide information on the actual day & time closures.
Also note that the long-term South channel is scheduled to close on Tuesday, May 29, 2018 and would remain closed through September.
Thanks again for your understanding and as always, please don’t hesitate to contact me if you have any comments or concerns.
Josh Perry
Project Manager
American Bridge Company
973-445-8579 - Cellular