Fwd: UPDATE No. 12: Notification of Temporary Navigable Channel Closures at Spuyten Duyvil Bridge

1 view
Skip to first unread message

Nancy Brous

unread,
Jul 17, 2018, 9:30:59 AM7/17/18
to nyc watertrail list, Pier 84 paddlers, Yprc Google Group, greenl...@googlegroups.com, nyckayaker**


---------- Forwarded message ---------
From: Josh Perry <Jpe...@americanbridge.net>
Date: Tue, Jul 17, 2018 at 9:01 AM
Subject: UPDATE No. 12: Notification of Temporary Navigable Channel Closures at Spuyten Duyvil Bridge
To: Josh Perry <Jpe...@americanbridge.net>


Spuyten Duyvil Project Update No. 12 (week ending July 21, 2018):

 

Good morning,

 

Attached is an updated schedule of events that depicts the dates we anticipate remobilizing the LCL crane to reset the truss back on the center pier. We have moved the lift operation to begin on July 30, 2018. The week-long event would once again close the North channel for the week, and as we get closer to this work we will continue to keep everyone aware of the dates.

 

Thank you, and please contact me if you have any questions.

 

Josh Perry

Project Manager

 

American Bridge Company

973-445-8579 - Cellular

 Logo-Safety.jpg

 


Reply all
Reply to author
Forward
0 new messages