Prevent stage re-run / Force running full pipelines

12 views
Skip to first unread message

Matt Gaunt-Seo

unread,
May 11, 2023, 12:56:56 PM5/11/23
to go-cd
Hi,

Is it possible to prevent users from re-running stages and require a pipeline to be run from start to finish?

A number of pepole are struggling to follow the history of events from the GoCD UI when people re-run stages either on the latest pipeline run OR older pipelines.

Disabling re-running of a stage would force users to trigger a new run of the pipeline and make the UI a little easier to follow what was last deployed.

Thanks,
Matt

Sriram Narayanan

unread,
May 11, 2023, 1:22:47 PM5/11/23
to go...@googlegroups.com
Not possible in GoCD currently.

I’ve catered to this in the past with a workaround - setting up a preceding pipeline that people can trigger which then leads to triggering this downstream pipeline.

Just a workaround.

— Sriram 

--
You received this message because you are subscribed to the Google Groups "go-cd" group.
To unsubscribe from this group and stop receiving emails from it, send an email to go-cd+un...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/go-cd/ac562b6e-b3fb-4dc4-a9da-bd2bbfb61c95n%40googlegroups.com.
Reply all
Reply to author
Forward
0 new messages