CertainlyIn HubSpot, you can indeed reference data from associated records using calculated properties. Calculated properties allow you to perform calculations or concatenate data from multiple properties, including properties from associated records. (More information here)
The question was in the custom equation option. There doesn't appear to be a current option to use associated records in the custom calculation area. All options that are available are only from that exact object.
I want to use my own formula to calculate duration. I've added a Calculated Duration column, but I can't select that column in my project settings. What governs what column you can select for your duration column?
You are correct: you cannot place a formula in the Duration column if you're using that column in your Project Settings for Duration (see: Areas where formula use is restricted). This is because the sheet already applies a background formula to that column - if you select a Start and End date, the Duration will populate based on the Working Days set in your Project Settings.
You can add another, regular column in your sheet to perform calculations and determine durations, but this column cannot then be selected in your Project Settings. Please let the Product team know of your use-case and why you would like to have formulas in this column by filling out this form, here.
I have learned that if it is not a column formula that I can select my Calculated Duration as my duration column, however, the formula gets erased at that point and it just becomes a regular duration column.
Thanks @Genevieve P. . I marked your response as not answering my question, but I guess it did: it isn't possible. I can't go back and change that because once you select one it disappears, but feel free to mark it as answered by you if you wish. I did submit feedback to the linked form.
Thank you for providing your feedback through the link! The Product team reviews each of these submissions so it's a great way to let them know how you're using Smartsheet and any enhancements that you think would help with your current set-up.
But given the fact that we cannot use formulas in the Duration column, I'm unable to place the 3PE in it. Furthermore, if I calculate and store the 3PE in some other column, then also there's no connection between that other column and the Duration column (meaning whenever I change the 3PE data, I've got to update the Duration column manually!)
You've outlined how Duration works in Smartsheet, yes. Either you can use the built-in Duration column, or have your own way of calculating duration in another column but it won't be synced to your other Project columns or Gantt chart.
I opened a support ticket, but I can't close this pop-up no matter what I click or what browser I use and I'm wondering if anyone has any insight. I'm LOCKED OUT of my work because of some stupid UI refresh alert. ?
I am attempting to use the INDEX(MATCH) formula with the range being a column that is calculated with a formula. I keep getting a #NOMATCH message - can MATCH only work on a column that has actual values (i.e., not values calculated from a formula)?
Try forcing your calculated term to a number by wrapping it in a VALUE function. Also we will add a zero to the end of the MATCH function to indicated unsorted data. In the countless Index/Matches I've done, I always add the zero.
I'm trying include a date range with counting the number of applicants within various depts, in certain date ranges, but it's saying incorrect argument set. =COUNTIFS(DISTINCT([Name of Requestor]:[Name of Requestor], [Submission Date]:[Submission Date], AND(@cell > DATE (2023, 9, 30), @cell
Hi @sjones.3795 - Welcome to AWS QuickSight community and thanks for posting the question. This is strange, is it possible to share the calculation field definition/formula that you are trying to add. This will help me replicate the issue at my side.
Hi Sydney - Thanks for your response. I tried to recreate the formula at my side and able to run without any errors. Pls use locate and If Else to achieve this. Can you pls try and let me know if it helps?
I haven't yet been able to find a way to dynamically edit a worksheets own constant. But you can update the XML of a workflow from one to another workflows, so all you do is import the workflow in the input tool, formula tool with find and replace and output tool. This way when the next WF is opened it will have been updated with the new constant.
If you intend to have different formulas in the same column in a table, you can turn off this "annoying" feature of excel globally as shown below. I wish I could turn it off, per table or at least per sheet.
I'm using Python, and I can get the Calculated Value as a ScheduleField using the code below, but I can't figure out a way to access the Formula. Perhaps this isn't possible in the API at the moment? If it is, any help would be appreciated!
Can you edit it manually in the user interface? If not, the API will probably not support this either. If yes, there might be a way somehow. To discover how, perform the manual operation and research what exactly changed where, e.g., using RevitLookup:
I have tried to use the Revit Lookup tool on the schedule, but I couldn't find anything of use. The farthest I can get is to get the Calculated Value, but I don't know how to access the Formula in the calculated value to be able to edit it.
Later the lookup column was moved, so I had to change the formula to lookup column 10 instead of 9: =VLOOKUP([@[Last Name]]&" "&[@[First Initial]],LookupLastF,10,FALSE). I had to manually copy the formula through the column, because there were exceptions -- i.e. some items overwrote the formula with manually entered values.
The problem is every time a new row is inserted into the table, the old formula is copied to the row instead of the corrected formula. So a default based on the original formula must still exist somewhere. How do I change it to the new formula?
Microsoft SharePoint Foundation formulas for calculated fields are based on Microsoft Excel functions and syntax. However, Microsoft supports only those functions mentioned on this page for use in SharePoint Foundation calculated fields. For example, the Excel function MID is not supported.
All example formulas in this topic use commas "," as the parameter delimiter character. In some countries, the comma is reserved for use as the decimal mark. In such countries, users creating a calculated field must use semi-colons ";" as the delimiter character. Regardless of which character is used when the field is created, the formula works on lists in SharePoint websites anywhere in the world. SharePoint automatically changes the delimiter character to the one that is appropriate for the language/culture of the current page. For example, suppose the following formula is created on a website whose culture setting is fr-fr (France): =IF(Number1>Number2;5;10). If the website's culture is then changed to en-us (United States), the formula changes automatically to: =IF(Number1>Number2,5,10).
You can use the following formulas to test the condition of a statement and return a Yes or No value, to test an alternate value such as OK or Not OK, or to return a blank or dash to represent a null value.
You can use the following formulas to perform calculations that are based on dates and times, such as adding a number of days, months, or years to a date, calculating the difference between two dates, and converting time to a decimal value.
To present the result in the standard time format (hours:minutes:seconds), use the subtraction operator (-) and the TEXT function. For this method to work, hours must not exceed 24, and minutes and seconds must not exceed 60.
A Julian date refers to a date format that is a combination of the current year and the number of days since the beginning of the year. For example, January 1, 2007, is represented as 2007001 and December 31, 2007, is represented as 2007365. This format is not based on the Julian calendar.
You can use the following formulas to perform a variety of mathematical calculations, such as adding, subtracting, multiplying, and dividing numbers; calculating the average or median of numbers; rounding a number; and counting values.
You can use the following formulas to manipulate text, such as combining or concatenating the values from multiple columns, comparing the contents of columns, removing characters or spaces, and repeating characters.
Summary
Social Security benefits are typically computed using "average indexed monthly earnings." This average summarizes up to 35 years of a worker's indexed earnings. We apply a formula to this average to compute the primary insurance amount (PIA). The PIA is the basis for the benefits that are paid to an individual.
The formula used to compute the PIA reflects changes in general wage levels, as measured by the national average wage index. We have constructed examples to illustrate how retirement benefits are calculated.
Average Indexed Monthly Earnings (AIME)
When we compute an insured worker's benefit, we first adjust or "index" his or her earnings to reflect the change in general wage levels that occurred during the worker's years of employment. Such indexation ensures that a worker's future benefits reflect the general rise in the standard of living that occurred during his or her working lifetime.
3a8082e126