Is it possible to change the top tier in timne and date format to year

30 views
Skip to first unread message

apeksha gupta

unread,
Dec 21, 2011, 8:32:59 AM12/21/11
to Gantt
In the scroll down section of 'Select time/date display format' the
drop-down for tier 1,2,3, has only month,week,day. How do I change
tier 1 as 'year' format?

Timios Inquiry

unread,
Dec 21, 2011, 7:44:54 PM12/21/11
to ga...@googlegroups.com
Hi, just double click it or click Format Time scale...

--
You received this message because you are subscribed to the Google Groups
"Gantt" group.
To post to this group, send email to ga...@googlegroups.com.
To unsubscribe from this group, send email to
gantt+un...@googlegroups.com.
For more options, visit this group at
http://groups.google.com/group/gantt?hl=en.