I seem to have an 800-day limit built into task durations. Even when
hovering over the task bar shows a longer duration, the editing box
shows 800 days. If I enter a longer duration, it is reduced to 800.

Timios Inquiry/Support

unread,
Jul 16, 2010, 5:30:01 AM7/16/10
to ga...@googlegroups.com
Yes, there is a limit of 800 days for a task duration? Do you need more? If yes, please write in and we can provide a tweak on the configuration file to increase it.


Timios Support

--
You received this message because you are subscribed to the Google Groups "Gantt" group.
To post to this group, send email to ga...@googlegroups.com.
To unsubscribe from this group, send email to gantt+un...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/gantt?hl=en.

AHearer

unread,
Jul 16, 2010, 1:44:31 PM7/16/10
to Gantt

Thanks for the reply: I was beginning to think I was going mad! Yes,
I'm charting a three-year project and there is one low-level task
which spans the whole period. I was beginning to think I would have to
work around it in some way. If you can tell me how to tweak the
configuration file that would be very helpful.

Tony Harker

On Jul 16, 10:30 am, "Timios Inquiry/Support" <inqu...@timios.net>
wrote: