When I add a holiday into an already existing chart, it doesn't appear
in the gantt chart. I am on the latest version (2.0.3714.28715).

It ***sometimes appears after I exit and go back in. I can't
determine why it would work for some days, but not others.

Gantt Designer Support/Inquiry

unread,
Mar 25, 2010, 3:46:52 AM3/25/10
to ga...@googlegroups.com
Hi, thank you for the feedback. We couldn't reproduce the exact problem.
Do note that there are two sets of holidays: the system's and a chart's. The
system's holidays are not applied to a chart unless you indicate so.

When you click Tools Calendar, you see two tabs representing the two sets of
holidays. Check the check box at the bottom if you want the chart to simply
follow the system's holidays. Otherwise only the holidays on the second tab
will apply to your current chart.

Hope the above helps.