>>Is there any way to balance the loads of the resources in a resource park that meets the requirement of a MO?
>>for example. I want to evenly distribute the MOs on the same type resources in a resource park that MO requires so that each resource's ultilization is balanced. I have tried the penalty and cost, but neither works.
Some hints:
- Fill in a dummy cost for each resource, and make sure the search mode is set to “cost + penalty” in the operation-resource and resource tables
- Verify the search by setting the parameter “plan.loglevel” to 2, and have a look at the log file of a planning run. You should be able to recognize sections where the algorithm is evaluating each resource.
- This will not split a requirement over multiple lines. It will plan eg sales order A on resource 1 and sales order B on resource 2. If you want to plan a single sales order across multiple resources, you can use the operation.size_max field to divide a large requirement across a number of smaller MO.
Johan De Taeye
Mob: +32 477.385.362
Skype: jdetaeye
Visit us at https://frepple.com
--
You received this message because you are subscribed to the Google Groups "frePPLe users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to frepple-user...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/frepple-users/ce294366-e947-4dfc-bb3f-b790f02c4a51n%40googlegroups.com.