Hi Guys,
my question is : how can I manage different unit of measure for the capacity calculation of different resources?
Supposing to have 2 main groups of machines:
- ultrasonic cut 
-cut and fold 
where the ultrasonic machines have the meter as unit of measure and 
where cut and fold  machines have pieces as unit of measure,
 how can I setup frepple to manage this kind of production?
Thnaks in advance for your help.
Rgds
Paolo

Johan De Taeye

unread,
Apr 30, 2013, 3:10:52 PM4/30/13
to freppl...@googlegroups.com

Ciao Paolo,

 

All values in frePPLe are unit-less.

 

To model your scenario, you will need to do some math to set the time-per duration of the flow models correctly.

I.e. take into account the unit conversion explicitly when preparing the input data for frePPLe.

 

Johan

--
You received this message because you are subscribed to the Google Groups "frePPLe users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to frepple-user...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

jdetaeye

unread,
Apr 30, 2013, 3:21:54 PM4/30/13
to frePPLe users
>>... of the flow models correctly.

Correction: ... of the operation models.


Johan

Paolo Tofoni

unread,
Apr 30, 2013, 3:42:10 PM4/30/13
to freppl...@googlegroups.com
Ciao Guys,
Thank a lot for your prompt reply ... Thus it means that to set the setup matrix I have to indicate each possible combination haven't I?

Johan De Taeye

unread,
Apr 30, 2013, 4:04:26 PM4/30/13
to freppl...@googlegroups.com
You will potentially have a lot of different operations, yes.
But the setup matrix isn't made any more complicated by that: different
operations can use the same setup, and you can also wildcards in defining
the changeovers.

FYI: the solver doesn't handle optimization of the changeovers yet.
Depending on the importance of changeovers in your plant, the quality of the
plan may be affected.