Does anyone know what is the best way to plan a painting line?
I have an epoxy coating line with a chain conveyor. I can hang parts below each other and next to each other.
One tour of the line takes roughly 30minutes, but since it's a continuous loop I can continuously hang pieces and take off pieces.
Until now we always considered painting of pieces as one full day. It doesn't matter if I have 1 order or 10, we just take one day to start the ovens, prepare the line, paint the pieces, unload the parts,...
When I set the operation as time_per (30 minutes) then my total time is way off.
If I set the operation to fixed_time (8hours) then the total time is okay for a single order, but if I have multiple orders it takes X times 8 hours which is also way off.
Can I somehow create a schedule so when I need parts at the assembly, minimum 1 day before it just lists all the orders at the painting line without really scheduling it?