Hi, I'm fairly new to frepple so excuse me if I ask an obvious question.

I notice that a lot of the manufacturing orders are being split up in multiple MO's. Also I notice that the quantity is getting divided in fractions. eg. it shows a planned quantity of 84.70588235 which doesn't make sense as I can't make 0.7 of a part
How can I avoid this? Is there some setting to make?

Capture.PNG

Johan De Taeye

unread,
Jun 7, 2021, 6:04:44 AM6/7/21
to freppl...@googlegroups.com

Hi Tim,

 

The fields “size_minimum” and “size_multiple” in the operation table should allow you to control this: see https://frepple.org/docs/current/model-reference/operations.php

 

Johan De Taeye

Mob: +32 477.385.362

Skype: jdetaeye

Visit us at https://frepple.com

--
You received this message because you are subscribed to the Google Groups "frePPLe users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to frepple-user...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/frepple-users/f99996b3-e484-4291-93d5-98e78462449an%40googlegroups.com.

Tim Snels

unread,
Jun 7, 2021, 6:53:00 AM6/7/21
to frePPLe users
Hello Johan,

Thank you for the quick reply. By setting the size_multiple to 1 it seems to have solved the issue with a part being divided in a fraction. 
I understand the function of the size_minimum but I can't really set a minimum quantity. It is made to order and I can get an order for 5pcs but also for 1000pcs. Is there another way to make sure MO's don't get split up so I don't loose the setuptime?

Johan De Taeye

unread,
Jun 7, 2021, 7:11:01 AM6/7/21
to freppl...@googlegroups.com

Hi Tim,

>>It is made to order and I can get an order for 5pcs but also for 1000pcs. Is there another way to make sure MO's don't get split up so I don't loose the setuptime?

There are 2 measures to take to prevent this splitting:

  • Set the “minimum shipment” field in the demand table equal to the “quantity”.
    This prevents the solver from delivering a sales order partially, and force a single full delivery.

  • Set the parameter “allowsplits” to “false”.  
    This prevents the solver from planning quantities that cover less than the requested quantities.

Tim Snels

unread,
Jun 7, 2021, 10:05:19 AM6/7/21
to frePPLe users
That did the trick, thanks a lot!