Drilling Sequence determined by confidence level; hence the following
parameter is considered with no 1 as the most important.
1. Proven Volumetric Estimate.
2. Permeability.
3. Reservoir Thickness.
4. Drawdown / Productivity Index.
5. Oil Rate.
These are given in well test results Block 2.
> --