Dear all,
Attached is the reservoir part in Table and Graph form, which include the information that might be related to Drilling, P.Tech, Facilities, Abandonment, etc.
Production Profile
Well number & location
EUR for each layer
Life of each well - time period for production
Production rate, Injector rate
Np, GOR, WCT, Gas Rate, etc.
I will write report using all this data generated.
Pok Cek, after talking bout both natural depletion & water injection scheme, can u do cost analysis for both scenario?
Just a simple one, include cost/investment needed for drilling/completing producers & injectors for both scenario.
(note: 3 appraisal well used back for both cases
, so just need to consider the completion cost only maybe?)
Then estimate the revenue generated based on the EUR for both cases, (u might just estimate by
30,000 Mstb produced for Natural
Depletion,
51,000 Mstb for Water Injection.
Since both life are 9 years, so no need compare payback period i guess, just (revenue-cost) for both cases.
Tips: Ensure water injection earn more, cos later part all based on water injection scheme.
Fuad & Azri,
For Reservoir Management Plan, some completion strategy (eg. sand control, gas lift, etc.) should be included as part of RMP?
I noticed the previous work did include Uncertainties
& Potential Problems. But i check back the job distribution, didn't notice who's taking charge of this part, or i miss out this point? (Pictures given by Nody can just refer).