1 - How I add items to a production order while it is in progress. For example: Item A BOM uses 2 raw materials to be created, but as he was making, it hurt 1 raw material and must be replaced. 

2- How should I do it? It is possible? - I build a report that shows me the raw materials that were planned to be used to manufacture the Item A vs those actually consumed? ex: Planned Qty 2 Used Qty 3

Rushabh Mehta

unread,
Jul 17, 2014, 12:41:06 AM7/17/14
to erpnext-u...@googlegroups.com
I guess you could cancel Production Order and create a new one.

OR

Keep things as they are and make the adjustment directly in your (material issue and backflush) stock entries and leave a comment.


--
You received this message because you are subscribed to the Google Groups "ERPNext User's Forum" group.
To unsubscribe from this group and stop receiving emails from it, send an email to erpnext-user-fo...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/erpnext-user-forum/258e0e1e-5b2a-499f-a3c9-c59d84b6d8e4%40googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

Reply all
Reply to author
Forward
0 new messages