Daily Scrum report for 2016/08/12:

1) What did I accomplish on 2016/08/11?

- Completed the task of implementing the upgrade process in Engelsystem with the changes in UI to enable and disable the updates.
(Issue: https://github.com/fossasia/engelsystem/issues/162)
(Issue: https://github.com/fossasia/engelsystem/issues/219)
(PR: https://github.com/fossasia/engelsystem/pull/220)

- Updated the .travis.yml file
(Issue: https://github.com/fossasia/engelsystem/issues/215)
(Issue: https://github.com/fossasia/engelsystem/issues/191)
(PR: https://github.com/fossasia/engelsystem/pull/217)

2) What will I do on 2016/08/12?

- Document the upgrade process in the repository.
(Issue: https://github.com/fossasia/engelsystem/issues/162)

- Write a blog post on implementing the upgrade process.

- Work on Travis.yml file.
(PR: https://github.com/fossasia/engelsystem/pull/217)

3) What obstacles are impeding my progress?

- Currently, there are no obstacles impeding my progress.

--