MOM for yesterday's meet with Keppel and MA folks

5 views
Skip to first unread message

Ambujakshya ghosh

unread,
Feb 21, 2014, 1:12:05 AM2/21/14
to TN Gupta, Ambujakshya ghosh, Kousik Majilya, surya bhaduri, amites...@bajajallianz.co.in, Barun Rai, bipla...@techmahindra.com, Mickey Kohli, amalendu kumar, Ashis Mohanty, nath...@yahoo.co.in, elitagar...@googlegroups.com, elitavist...@googlegroups.com, Ajay Kumar Singh, Rathindra nath Sur
All,

This is for all those who are not in facebook. MOM for yesterday's meeting with Keppel and MA personnel is already posted in FB by Souvik. Reposting it here for the benefit of others:

-          KMDPL will let resident/buyers know whenever there will be any stake sale.
- New builder will carry forward all present builder’s liability including electricity, defect rectification and completion of all facilities as per DoC.
- Phase 2 will begin this year
- Dedicated electricity meter from state electricity board can only be installed provided Keppel sale land to authority inside our condo to set up sub-station or 51% registration of residents in owner’s association or forming co-operative.
o Land inside the condo can’t be sold to authority as this our property part of common area.
o 51% registration of residents out 1388 units (including Phase 1 & 2) is out of question at this moment.
o Co-operative can’t be formed due to its legal limitation and few resident
s who have multiple flats objected co-operative formation. On top of that co-operative has to be in place before construction commences.
- KMDPL gets bulk electricity supply of 2000 KVA under commercial rate and latest bill amount was INR 17 lakhs. Major part of the bill is fixed cost which KMPDL has to pay whether they use the full load or not. Residents’ consumption was very minimal and rest of load goes unused.
o KMDPL is looking for option to reduce the load of 2000KVA for the fixed cost can be reduced.
o Residents will be charged on subsidized domestic rate (as per electricity board tariff) through ‘demand note’ which will include units consumed in units, common area meter and diesel usage. Residents propose to add common area meter and diesel usage from maintenance take from owners. On this context Iman raised concern that in that case the maintenance money paid by us for 36 months will be over sooner than that.
o Billing procedure and what to include is still under discussion by KMDPL.
o Another perspective is the owners who have rented their property are asking Keppel to charge demand note so the same can be charged to tenants.
- Questions asked about malpractice related to hooking meter and access to unauthorized people to meter room. Residents suggested installation of tamper-proof meter and limited access to meter rooms.
- Adrian agreed that at present low load capacity meter installed (e.g For 2 bhk, max 2 ACs can run in parallel where provision is for 4 and for 3 bhk, max 3 ACs can run in parallel where provision is for 5. MA is going to explore on higher load capacity of meter.
- Maintenance cost paid us will be audited by 31st Mar and the same report will be shared with us.
- Related to defect rectification, Adris ordered Managing Agent (MA) and Project’s technical team
o All broken/cracked tiles to be replaced through contractor who did this work.
o All broken drain covering slabs and gap between the gaps to be rectified.
o Whatever painting/plastering for the building needs to be completed.
o Related to water seepage in parking from water bodies at podium needs to be rectified.
- Related to maintenance
o MA is going to appoint a gardener or landscape artist to restore greeneries inside the condo.
o Both fountains to be functional and to be cleaned periodically.
o Stagnant water has to be replaced with fresh water periodically.
o Drain surrounding the parking has to be cleaned.
o Dustbins requested to be placed at floors where residents are staying.
- Related to condo security they will explore the vulnerabilities highlighted by us.
- Clubhouse facilities are at discretion of builder as S&P agreement doesn’t have mentioned what are the facilities will be provided by builder. Any amenities addition will be used out association or maintenance money.
o On enquiring about pool table we were informed each will cost INR 65K but residents challenged that the same is half of the membership amount paid by one resident.
o TT board provided to us has transit damaged will be repaired.
- Adris informed us that even if any stake sale takes place, residents will be involved or informed pro-actively and will be informed and introduced to new builder formally once the stake sale is over.


Thanks to all residents/owners who took out time from their busy schedule to attend yesterday's meeting.

--
thanks and regards
Ambuj