Project Information
S.F. Public Works has partnered with the San Francisco Public Utilities Commission (SFPUC) and the San Francisco Municipal Transportation Agency (SFMTA) to complete infrastructure and safety improvements on Geneva Avenue from Mission Street to Prague Street and Mission Street between Geneva Avenue and Trumbull Street.
This scope of work will include sewer main replacement and rehabilitation work, curb ramp and pedestrian bulb-out installation, transit bulb-outs, Auxiliary Water Supply System (AWSS) settlement monitoring work, electrical and traffic signal upgrades, concrete street base replacement work (concrete roadwork) and pavement renovation.
Construction began in November 2022, with overall completion of the project expected in February 2026. In order to minimize any impacts associated with construction, and to ensure the entire limits aren’t under construction for the 3-year duration, this project will be completed in segments. A completion timeline has been placed on each segment to minimize the time it is under construction. There will be an overlap in segments as work is completed in one segment and starts on the next one. The segments are as follows:
Segment I
Geneva Avenue (Mission St. to Prague St.)
(Approximately 11 months / November 2022 – November 2023)
Segment II
Mission Street (Geneva Ave. to Russia Ave.)
(Approximately 10 months / October 2023 – August 2024)
Segment IV
Mission Street (Theresa St. to Trumbull St./ Hwy 280 overpass)
(Approximately 5 months / August 2024 – January 2025)
Segment III
Mission Street (Russia Ave. to Theresa St.)
(Approximately 11 months / January 2025 – February 2026)
Sewer service will not be interrupted during replacement of the sewer main. Please continue to use your household/business plumbing per the usual.
Please visit www.sfpublicworks.org/Mission-Geneva for additional information. To sign-up to receive electronic updates during construction, please click HERE.
|