Fwd: Paving Update

1 view
Skip to first unread message

LaVerne Biel

unread,
Oct 28, 2019, 6:01:35 PM10/28/19
to google group
FYI

Sent from my iPad

Begin forwarded message:

From: Kevin Shanley <Kev...@maxkuney.com>
Date: October 28, 2019 at 10:07:07 AM PDT
To: "Vazquez, Michele" <mvaz...@spokanecity.org>
Cc: Ben Stuckrath <be...@maxkuney.com>
Subject: Paving Update



 

The CSO project is scheduled to perform the final paving on October 31st. This will include the paving on Crestline St between Riverside and Sprague, Zips’ driveway entrance, as well as the alley just north of Zips. The intermittent, local street closures that have been common throughout the project will be done after this paving is completed. Your patience and understanding is much appreciated as this project is now winding down.

 

 

Kevin Shanley

Project Manager

Max J Kuney Co