| Points | Outcome | Remarks |
|
1)
Original Date of Booking to be mentioned in MOU
|
Original MOU date will be provided on Dreamz letter Head | |
|
2)
Carpet Area: |
68% to 70% carpet area has been commited | Letter should mentioned about the penalty clause if commitment not fulfilled |
|
3)
Amenities list that will be provided |
Common Hall, Height Adjustable Kitchen, Gym, Supermarket. | Letter should mentioned about the penalty clause if commitment not fulfilled |
|
4)
Project completion date |
No conclusion yet. Not sure but it was commited that within 14-16 months, project will be delivered | Confirm on completion date |
|
5)
Home Loan payment slabs as per the Bank norms |
No conclusion yet | Confirm on progress of the same |
|
6)
Cancellation amount refeund time line as per old MOU
|
Agreed the timeline will be 60/90 days as per old MOU. Same will be mentioned in new MOU | |
|
7)
Allotment letter
|
Will be shared soon. Some of them already received but many of them still waiting | |
|
8)
New Floor plan that is sent to BBMP for approval
|
No one ready to share floor plan. Pointing fingers to each other. | We as a customer have complete right to see the floor plan which is being send to BBMP for approval. Please look into it on priority |
|
9)
Most important Meeting with MD
|
No meeting arranged so far | From last 2 months, no meeting has been arranged. Inspite of commiting that meeting will be arranged between 2nd and 5th of Jan 2014, you were unable to arrange the same |
--
You received this message because you are subscribed to the Google Groups "Dreamz Ekadant" group.
To post to this group, send email to dreamz-...@googlegroups.com.
Hi,
Snehal I think the ovrall draft looks quite ok
I did get a reply as manisha has not been able to fix meeting with mr sachin nayak as he is out of station
She had also stated that prateek had solved all our queeries
I had reverted to her mail marking our group.
Regards
Chandan
--
--