I encountered a real nasty with WRKJOBSCDE yesterday.
We were running some scheduled testing and user TESTA scheduled the
jobs. His current data library was TESTLIB.
Then the user went into WRKJOBSCDE, using his live profile with a
current data library of LIVELIB, and entered a 10 to submit one of the
scheduled jobs.
It went onto the system and processed as TESTA, but the data library
was LIVELIB!!
I now realise that WRKJOBSCDE uses SBMJOB to process option 10. But I
still cannot believe that it is not using the current library of the
person who scheduled the job.
OK, rant over.
Neil
I had the same problem
after that I allways change time to *CURRENT
then a refresh (F5)
and then change time back to original
--
Ad,
pas de probl�me, que des solutions