Road closings for the week: 8/18/2025 to 8/25/2025

2 views
Skip to first unread message

inr...@bloomington.in.gov

unread,
Aug 15, 2025, 3:00:04 PM8/15/25
to cob_road...@googlegroups.com
This is an automated email message from inRoads.

inRoads is a digital service of the City of Bloomington to publish planned
and future road closings, lane reductions, parking reservations and more.
inRoads can be accessed online at http://bloomington.in.gov/inroads.

########################################################
Road events for next week, 8/18/2025 to 8/25/2025:
########################################################

-------------------------------------------------
## Allen St. Bridge ##
Bridge between S Morton and S Walnut (150-156 W Allen St)

W Allen ST from S Morton ST to S Walnut ST

January 7, 2020 to January 7, 2027
Road Closed; expect to detour, signage in place.
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
https://bloomington.in.gov/inroads/events/view?id=3798

-------------------------------------------------
## Poplars Redevelopment Project ##
400 E 7th St



February 17, 2025 to November 21, 2025
Lane Restriction; expect short delays, signage in place.
Sidewalk closure and protected bike lane diversion to accommodate crane use for the Poplar Building Redevelopment.
https://bloomington.in.gov/inroads/events/view?id=6277

-------------------------------------------------
## Duke 1-2 day closure of alleyway ##
1417 A S Walnut ST



March 15, 2025 to August 31, 2025
Road Closed; expect to detour, signage in place.
Replacement of overhead equipment on pole # 151-247. 1-2 day closure of the alley between S Walnut St and S Washington St occuring between 03/15/2025 and 08/31/2025. No overnight closure.
https://bloomington.in.gov/inroads/events/view?id=5970

-------------------------------------------------
## Longview Neighborhood Greenway Project ##
Longview Ave from Pete Ellis through to Smith Rd.

E Longview AVE from N Pete Ellis DR to N Glenwood AVE E
N Glenwood AVE E from E Morningside DR to E Longview AVE
E Morningside DR from N Glenwood AVE E to N Smith RD

March 31, 2025 to August 29, 2025 daily until August 29, 2025
Lane Restriction; expect short delays, signage in place.
Along Longview Ave between Pete Ellis and through to Smith Rd, there will be new curbs installed as well as new curb ramps and sidewalk in areas. There is a multiuse path being installed along the north side of Longview between Pete Ellis and Kingston. There will also be asphalt speed humps installed. There may be time limited road closures when the speed humps are installed.
https://bloomington.in.gov/inroads/events/view?id=6325

-------------------------------------------------
## Winslow, Rogers Resurfacing Project (Allendale to Sare) ##
Winslow Rd from Allendale east, then east on Rogers Rd to Sare Rd

E Winslow RD from S Allendale DR to S High ST
E Rogers RD from S High ST to S Sare RD

March 31, 2025 to July 15, 2025 daily until July 25, 2025
Lane Restriction; expect short delays, signage in place.
Winslow and Rogers Rd will be resurfaced from Allendale to Sare Rd. There are new curbs, curb ramps, and sidewalk being installed as well. There is also a median and rain garden being installed at Xavier Ct on Winslow Ave. A median at Spicewood Ln has been added to the project.
https://bloomington.in.gov/inroads/events/view?id=6326

-------------------------------------------------
## Duke Energy Lane Closure ##
2425 S Walnut St



April 1, 2025 to August 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 40994471, single day lane closure for replacing pole # 151-161 and installing new pole # MNI-12336 along West side of S Walnut Street. No overnight closure. Work will take 1 day, but please allow up to 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6288

-------------------------------------------------
## Kirkwood 2025 Pedestrian Season / Dining Closure ##
E kirkwood Ave



April 2, 2025 to November 14, 2025
Road Closed; expect to detour, signage in place.
Planned street closure of 1/2 of the 100 block, 300, 400, and 500 blocks of E Kirkwood from Walnut to Indiana.
https://bloomington.in.gov/inroads/events/view?id=6402

-------------------------------------------------
## Duke Energy Lane Closure ##
1140 E Carnaby St



May 1, 2025 to August 31, 2025
Lane Restriction; expect short delays, signage in place.
WO #52890955.

Replacing elbows on 4 separate pads in between S Westminster Way and Acadia Court S. Replacing 718' of underground cable. No work will actually be within the right of way other than the South side of E Winslow Road. We will need a lane restriction on E Winslow Road where we will have flaggers. No overnight closure.
https://bloomington.in.gov/inroads/events/view?id=6265

-------------------------------------------------
## Duke Energy Lane Closure ##
1606 S Rogers St



May 1, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
Lane restrictions for pole work
https://bloomington.in.gov/inroads/events/view?id=6275

-------------------------------------------------
## Thornton/Arden Greenway and S Washington Traffic Calming Project ##
Thornton Dr from Olive St to High St.
S Washington St from 1st St to Grimes Ln.

S Washington ST from E 1st ST to E Grimes LN
E Thornton DR from S Olive ST to S Oxford DR
E Arden DR from S Oxford DR to S High ST

May 8, 2025 to August 29, 2025 daily until August 29, 2025
Lane Restriction; expect short delays, signage in place.
Thornton Dr will have new curbs and new curb ramps placed throughout. There will also be asphalt speed humps installed. Along S Washington St, there will be asphalt speed humps installed. When speed humps are being installed, there may be a limited time road closure.
https://bloomington.in.gov/inroads/events/view?id=6324

-------------------------------------------------
## Duke Energy Lane Closure ##
594 594 E Graham PL



May 14, 2025 to August 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 55906571, 1 day lane closure of S Henderson street to Replace 2 poles on West side of S Henderson Street, and replacing 1 pole on on east side of S Henderson St.

No overnight closure. Work should take 1 day, but please allow for up to 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6294

-------------------------------------------------
## North Dunn Street Sidewalk Connection ##
N Dunn Street just North of E 17th Street



June 9, 2025 to August 8, 2025 weekly on Monday, Tuesday, Wednesday, Thursday and Friday until August 8, 2025
Lane Restriction; expect short delays, signage in place.
Intermittent flagging for 400ft of N Dunn Street.
https://bloomington.in.gov/inroads/events/view?id=6521

-------------------------------------------------
## Duke Energy Lane Closure ##
911 S High St



June 15, 2025 to August 31, 2025
Road Closed; expect to detour, signage in place.
WO # 42544987, Lane closure for Installing new pole # MNI-12597 along E side of S High Street. No overnight closure. Work should only take 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6270

-------------------------------------------------
## Duke Energy Lane Closure ##
610 E Hillside Dr



June 15, 2025 to August 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 42544905, lane closure for Installing pole # MNI-20134 along S side of E Hillside Drive. No overnight closure. Work should take one day, but please allow for up to 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6271

-------------------------------------------------
## QC Communications Boring work ##
2219 S Rogers St



June 24, 2025 to August 25, 2025
Lane Restriction; expect short delays, signage in place.
Using a mechanized bore machine to replace 52ft of coaxial cable in pipe crossing S Roger St just north of W Jud St. A lane closure and sidewalk closure are needed. Time frame of project 06/24/2025 to 08/25/2025. Construction should take no more than 2 days once started. Comcast JB0002250437
https://bloomington.in.gov/inroads/events/view?id=6555

-------------------------------------------------
## Bloomington Convention Center Site Preparation ##
302 S Walnut st



June 27, 2025 to January 26, 2026
Lane Restriction; expect short delays, signage in place.
This request is to accommodate site work necessary for the Bloomington Convention Center Project. The traffic controls would be in place from June 27th, 2025 through January 23rd, 2026. Other permits for various closure needs are also expected between phase completions.
https://bloomington.in.gov/inroads/events/view?id=6556

-------------------------------------------------
## ROW2025-04-1544 ##
Multiple locations within the city



July 1, 2025 to April 28, 2026
Lane Restriction; expect short delays, signage in place.
Single lane closures for Circuit Sectionalization
https://bloomington.in.gov/inroads/events/view?id=6676

-------------------------------------------------
## Duke Energy Lane Closures ##
315 E North Dr



July 1, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
WO #46704275, 1-2 days of lane closures per location
Sheet 1 - Replacing overhead equipment on pole # 765-564 on E side of S Walnut Street. Replacing pole # 161-169 on E side of S Walnut Street

Sheet 2 - Replacing pole # 164-173 on S side of E North Drive. Replacing pole # 164-174 on N side of E North Drive. Replacing overhead equipment on pole # 164-172 on N side of E North Drive.

Sheet 3 - Replacing pole #'s 174-456, 174-458, and 764-768 on N side of E North Drive.

No overnight closures. Please allow 3 business days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6384

-------------------------------------------------
## Crown Castle Small Cell Tower Work ##
720 N grant St



July 7, 2025 to December 20, 2025
Lane Restriction; expect short delays, signage in place.
SC-IN E 11th St 510454_0003

Location: In the ROW at the intersecting corner of E 11th St and N Grant St.

Type of work: Type of work: Equipment swap/upgrade of telecommunications equipment at an existing small cell site. See attached drawing for more details and scope of work.

Extent of Closure: Closure at the side of an intersection, Crosswalk closures and pedestrian detours - see pages 9 & 10 of submitted drawing.

Expected date and/or duration: 6/20/2025-12/20/2025
The work is estimated to take 3 days max with the lanes and sidewalks open during the evenings when the crew is not onsite.
https://bloomington.in.gov/inroads/events/view?id=6587

-------------------------------------------------
## Duke Energy Lane Closure ##
3874 S Laurel Ct



July 15, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 56247048
Sheet 1 - Replacing overhead equipment on pole # 173-250 on west side of S Walnut Street Pike.

Sheet 2 - Replacing pole # 153-257 on E side of S Walnut Street Pike. Replacing pole #'s 153-256 and 153-253 on W side of S Walnut Street Pike.

Sheet 3 - Replacing pole #'s 153-260 and 153-258 along E side of S Walnut Street Pike.

Sheet 4 - Replacing pole # 151-208 along W side of S Walnut Street Pike. Replacing pole #'s 179-898 and 151-207 along W side of S Walnut Street Pike.

Sheet 5 - Replacing pole # 171-200 along E side of S Walnut Street Pike.

Sheet 6 - Replacing pole # 151-197 along W side of S Walnut Street Pike. Replacing overhead equipment on pole # 763-221 along E side of S Henderson Street.

No overnight closures. Work will take 1 day in each location, but please allow for 7 business days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6335

-------------------------------------------------
## Duke Energy Lane Closure ##
2490 S Burberry Ln



July 15, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 42544946, lane closure for Installing new pole # MNI-20082 along S side of E Winslow Road. No overnight closure. Work will be completed in 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6272

-------------------------------------------------
## Duke Energy Pole Installation ##
2822 S Walnut Street Pike



July 15, 2025 to August 31, 2025
Road Closed; expect to detour, signage in place.
3 day lane closure on the west side of S Walnut St Pike just north of the intersection with S Henderson St to install a new pole. Work will occur in the date range of 07/15/2025 to 8/31/2025.
https://bloomington.in.gov/inroads/events/view?id=6221

-------------------------------------------------
## BSM Group Aerial and Boring Work ##
2750 E Buttonwood LN



July 24, 2025 to September 24, 2025
Lane Restriction; expect short delays, signage in place.
UG duct placement by directional bore place 1 - 2" duct and fiber optic cable at a minimum depth of 48". Boring along the roundabout of E Rogers Rd and S Sare Rd approx. 73' ( 24.33 ft²) and Overlash: (OL) existing strand with fiber optic cable. Work is located along S Sare Rd approx. 762'. Sidewalk closure and lane closure work for one 8 hour day. (SEE MOT)
https://bloomington.in.gov/inroads/events/view?id=6649

-------------------------------------------------
## Duke Energy Overhead Equipment Replacement ##
2315 S Rogers ST



August 1, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
Single day(1-2 hour) closure of the eastern lane of S Rogers st near W Coolidge Dr to replace overhead equipment on pole # 814-4444 at the North East intersection of W Coolidge Dr and S Rogers St. Closure will occur in the date range of 08/01/2025 to 11/30/2025
https://bloomington.in.gov/inroads/events/view?id=6176

-------------------------------------------------
## Duke Energy Lane Closure ##
327 S Rogers



August 1, 2025 to November 30, 2025
Road Closed; expect to detour, signage in place.
WO # 41372422, Replacing overhead equipment on pole # 814-4426 at 2721 S Rogers Street. Pole is on the south east side of W Country Club Dr and S Rogers Street intersection. No overnight closure. Work will take 1-2 hours.
https://bloomington.in.gov/inroads/events/view?id=6264

-------------------------------------------------
## Duke Energy Overhead Pole Equipment Replacement ##
2630 S Rogers ST



August 1, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
Single day(1-2 hour) closure of the eastern lane of S Rogers st near W Watson St to replace overhead equipment on on pole # 814-4433 at the north west intersection of W Watson St and S Rogers St. Closure will occur in the date range of 08/01/2025 to 11/30/2025
https://bloomington.in.gov/inroads/events/view?id=6174

-------------------------------------------------
## Hopwell West (S. Jackson Street & S. Rogers Street) ##
S. Rogers St from W 1st St and W 2nd St



August 4, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
The construction of one block of Jackson Street and the reconstruction of one block of Rogers Street, from 1st Street to 2nd Street. The project scope includes installation of new stormwater infrastructure, sidewalks, a multi-use path, and a protected bike lane.
https://bloomington.in.gov/inroads/events/view?id=6683

-------------------------------------------------
## Noth Walnut Street Resurfacing Project ##
North Walnut Street from the SR 45 Bypass to 400 feet north of N Old 37



August 4, 2025 to November 1, 2025
Lane Restriction; expect short delays, signage in place.
Curb ramp replacements, curb repair, guardrail repair, removal of excess pavement, and updates to signs and markings.
https://bloomington.in.gov/inroads/events/view?id=6682

-------------------------------------------------
## QC Communications Boring and Over lashing ##
489 W 10th St



August 8, 2025 to August 29, 2025
Lane Restriction; expect short delays, signage in place.
Parking lane closure, travel lane closures, alley closures, and sidewalk closures for UG duct placement by directional bore place 1-2" duct and fiber optic cable at a minimum depth of 48", as well as Overlash (OL) existing strand with fiber optic cable. Work taking place on east side of N Rogers St, under W 10th St, over W Maker Way, over N Madison St, and along and over the north/south alley between W 11th St and 10th St approx 1614' within ROW (see plans).

Lane restrictions and sidewalk closures will progress/move with the work. once the affected portion of the road/sidewalk has been completed, the closure/restriction will be removed. Work will be done road by road and will take approx. 2 - 4 hours each to complete. TA-28 has been added to print for clarity and will be followed for sidewalk closures. sidewalk closed signs placed in advance of closure/s and barricades in place at each point of closure.
https://bloomington.in.gov/inroads/events/view?id=6645

-------------------------------------------------
## Milling and Resurfacing on S Washington St ##
S Washington St from E Allen St to E Hillside Dr



August 11, 2025 06:00 am to 16:00 pm August 21, 2025
Lane Restriction; expect short delays, signage in place.
Lane Restrictions and No Parking on S Washington St from E Allen St to E Hillside Dr for milling and resurfacing.
https://bloomington.in.gov/inroads/events/view?id=6688

-------------------------------------------------
## Hopwell West (S. Jackson Street & S. Rogers Street) ##
W 1st Street from S Fairview St to S Rogers St



August 11, 2025 to September 8, 2025
Road Closed; expect to detour, signage in place.
The construction of one block of Jackson Street and the reconstruction of one block of Rogers Street, from 1st Street to 2nd Street. The project scope includes installation of new stormwater infrastructure, sidewalks, a multi-use path, and a protected bike lane.
https://bloomington.in.gov/inroads/events/view?id=6684

-------------------------------------------------
## Single lane restriction ROW2025-07-1785 ##
2110 E Covenanter- Southbound lane



August 11, 2025 to August 31, 2025
Road Closed; expect to detour, signage in place.
site improvements
https://bloomington.in.gov/inroads/events/view?id=6691

-------------------------------------------------
## ROW2025-07-1786 ##
S Cory Ln just south of the Intersection of 3rd St and S Cory Ln



August 11, 2025 to September 30, 2025
Lane Restriction; expect short delays, signage in place.
closure of south bound lane of S Cory Ln just south of the Intersection of 3rd St and S Cory Ln
https://bloomington.in.gov/inroads/events/view?id=6669

-------------------------------------------------
## ROW2025-07-1786- ##
Left hand turn lane of West bound 3rd street at the intersection of 3rd and S Cory Ln



August 11, 2025 to September 30, 2025
Lane Restriction; expect short delays, signage in place.
2 day closure between 08/11 and 9/30
https://bloomington.in.gov/inroads/events/view?id=6667

-------------------------------------------------
## E Cottage Grove ##
E Cottage Grove from N Indiana Ave to N Walnut St



August 12, 2025 to August 19, 2025
Lane Restriction; expect short delays, signage in place.
Lane Restrictions and No Parking for milling and resurfacing.
https://bloomington.in.gov/inroads/events/view?id=6695

-------------------------------------------------
## Single lane closure ROW2025-07-1770 ##
West bound lane of E Miller @ 927 E Miller



August 12, 2025 to August 19, 2025
Lane Restriction; expect short delays, signage in place.
Sidewalk work
https://bloomington.in.gov/inroads/events/view?id=6694

-------------------------------------------------
## ROW2025-07-1771 - Single lane closure ##
Eastbound lane of Miller at 1800 S Huntington Gardens



August 12, 2025 to August 19, 2025
Lane Restriction; expect short delays, signage in place.
Single lane Closure
https://bloomington.in.gov/inroads/events/view?id=6692

-------------------------------------------------
## HUB 2 Utility Work ##
205 E 17th St



August 12, 2025 to September 19, 2025
Road Closed; expect to detour, signage in place.
Lane restrictions/intermittent closures of 1300-1400 Block N. Lincoln St 8/12/25 to 9/19/25
Lane restrictions/intermittent closures of 200 Block E. 19th St 8/12/25 to 9/19/25
Lane restrictions/intermittent closures of 1300 Block N. Washington St 8/12/25 to 9/19/25
https://bloomington.in.gov/inroads/events/view?id=6696

-------------------------------------------------
## Duke Energy Lane Closure ##
2106 E 3nd St



August 15, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
WO # 42544989, 1 day lane closure for replacing overhead equipment on pole # 167-653 along the east side of S High Street. No overnight closure. Work will take 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6287

-------------------------------------------------
## Duke Energy Lane Restriction ##
2425 S Rogers



August 15, 2025 to September 30, 2025
Lane Restriction; expect short delays, signage in place.
WO 40995878, Replacing overhead equipment (Crossarm, clevises, and pin insulators) on pole # 814-4442. Lane restriction will take place on East side of S Rogers street, and traffic flagging will take place for Northbound traffic on S Rogers Street. Work should take only 1 day, but please allow for 3 days in case of inclement weather. No overnight closure. Work will be completed using a bucket truck.
https://bloomington.in.gov/inroads/events/view?id=6266

-------------------------------------------------
## Duke Energy Lane Closure ##
1805 S Walnut St



August 15, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
WO # 4254498, 1 day lane closure on east side of S Walnut St for removing electronic relcoser on pole # 151-134 along east side of S Walnut Street. No overnight closure. Work will be completed in 1 day, but please allow for up to 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6285

-------------------------------------------------
## Duke Energy Lane Closure ##
1906 E Hillside



August 15, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
WO # 42544994, Installing new pole # MNI-20164 Along SW corner of E Hillside Drive and S Clifton Avenue. No overnight closure. Work should take 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6273

-------------------------------------------------
## Milling and Resurfacing on S Lincoln St ##
S Lincoln St from E Hillside Dr to E 1st St



August 18, 2025 06:00 am to 16:00 pm August 28, 2025
Lane Restriction; expect short delays, signage in place.
Lane Restrictions and No Parking on S Lincoln St from E Hillside Dr to E 1st St for milling and resurfacing.
https://bloomington.in.gov/inroads/events/view?id=6689

-------------------------------------------------
## CBU Stormwater System Work ##
E Hunter Ave from S Eastside Dr to S Rose Ave



August 18, 2025 to August 22, 2025
Lane Restriction; expect short delays, signage in place.
Beginning Monday, August 18, 2025, lane restrictions will be in place on E Hunter Ave from S Eastside Dr. to S Rose Ave. These temporary restrictions are necessary to allow CBU crews to safely and efficiently complete upgrades to the stormwater system. Work is expected to be completed by Friday, August 22, 2025, weather permitting.
https://bloomington.in.gov/inroads/events/view?id=6662

-------------------------------------------------
## Lineal Boring Work ##
1601 W 3rd St



August 18, 2025 to August 20, 2025
Lane Restriction; expect short delays, signage in place.
2-3 days of Lane closures on the southern lane on W 3rd St and Westplex Ave to bore from pole #125 along 3rd st down s westplex ave. going to 1555 w 3rd st total of 500' also setting 1 3'x 4' hand hole. 4-bore pits 3' x 4' in grass. A057ZZ3
https://bloomington.in.gov/inroads/events/view?id=6700

-------------------------------------------------
## Kinser Ridge -- FULL CLOSURE OF W ACUFF ##
1030 W Acuff



August 18, 2025 to September 1, 2025
Road Closed; expect to detour, signage in place.
Full closure of W Acuff
https://bloomington.in.gov/inroads/events/view?id=6712

-------------------------------------------------
## Southbound Lane Closure on S Rogers St. ##
Southbound lane of S Rogers St, beginning at W Hillside Dr. and ending at the north entrance of the Duke Substation.



August 20, 2025 to August 21, 2025
Lane Restriction; expect short delays, signage in place.
Crider and Crider will be performing work on a sewer relocation project on S Rogers St near the intersection of W Hillside Dr. Beginning on 8/20, the southbound lane of S Rogers St. will be closed. Crews will be flagging for normal traffic, but there will be a detour in place for larger trucks. Lane is expected to be reopened 8/21.
https://bloomington.in.gov/inroads/events/view?id=6713

-------------------------------------------------
## 2025 Pridefest ##
Kirkwood from Walnut to Indiana and Grant from 6th to 4th



August 22, 2025 to August 25, 2025
Road Closed; expect to detour, signage in place.
Kirkwood from Walnut to Indiana will be closed Fri 8/22 to Mon 8/25; Grant from 6th to 4th will be closed Sat 8/23 to Sun 8/24
https://bloomington.in.gov/inroads/events/view?id=6701

-------------------------------------------------
## IU Summer Fire Fest ##
7th from Indiana to Woodlawn



August 23, 2025 16:00 pm to 02:00 am August 24, 2025
Road Closed; expect to detour, signage in place.
IU Summer Fire Fest
https://bloomington.in.gov/inroads/events/view?id=6702

########################################################
Future road events
########################################################

-------------------------------------------------
## ROW2025-07-1736- 3 day single lane closure - Between 08/25/2025 and 09/15/2025 ##
1030 W Acuff RD



August 25, 2025 to September 15, 2025
Lane Restriction; expect short delays, signage in place.
DUKE ENERGY
-1030 W Acuff Rd
-Install pad mounted equipment and bore ~230 ft of cable on the northwest side of W Acuff Rd
-Close southbound lane of W Acuff Rd
-Work will take three days between 8/25-9/15
https://bloomington.in.gov/inroads/events/view?id=6704

-------------------------------------------------
## ROW2025-07-1734 ##
2515 S Rogers ST



August 25, 2025 to September 9, 2025
Lane Restriction; expect short delays, signage in place.
-WO 57889070
-2515 S Rogers St
-Relocate overhead service line
-Close northbound lane of S Rogers St, close sidewalk on east side of S Rogers St. Pedestrian crossing signs will be located at Rogers St X Graham Dr and Rogers St X W Ralston Dr
-Work will take two days within 8/25/25-9/9/25
https://bloomington.in.gov/inroads/events/view?id=6626

-------------------------------------------------
## Duke 1-2 day closure of W Dodds alleyway ##
508 W Dodds St



August 27, 2025 to October 27, 2025
Road Closed; expect to detour, signage in place.
WO # 52851282. 1-2 Day closure of the alleyway between W Dodds St and W Wylie St adjacent to 508 W Dodds St occuring between 08/27/25 and 10/27/25. Replacing overhead equipment on 5 poles. No overnight closure.
https://bloomington.in.gov/inroads/events/view?id=5973

-------------------------------------------------
## 4th Street Festival ##
See Map.



August 29, 2025 08:00 am to 21:00 pm August 31, 2025
Road Closed; expect to detour, signage in place.
4th Street Festival (www.4thstreet.org/)
https://bloomington.in.gov/inroads/events/view?id=6623

-------------------------------------------------
## Milling and Resurfacing on E Cottage Grove Ave ##
E Cottage Grove Ave from N Walnut St to N Indiana Ave



September 1, 2025 06:00 am to 16:00 pm September 11, 2025
Lane Restriction; expect short delays, signage in place.
Lane Restrictions and No Parking on E Cottage Grove Ave from N Walnut St to N Indiana Ave for milling and resurfacing.
https://bloomington.in.gov/inroads/events/view?id=6654

-------------------------------------------------
## ROW2025-07-1768 ##
Southbound lane of Fountain at 2110 W Fountain DR



September 4, 2025 to September 19, 2025
Lane Restriction; expect short delays, signage in place.
-Install transformer and overhead wire
-Close southbound lane of W Fountain Dr
-Work to take two days between 9/4 and 9/19
https://bloomington.in.gov/inroads/events/view?id=6675

-------------------------------------------------
## Crown Castle Small Cell Tower Work ##
1314 N Eagleson Ave



September 8, 2025 to March 8, 2026
Lane Restriction; expect short delays, signage in place.
SC-IN E 17th St 523288_0167

Location: In the ROW at the corner of E 17th St and the private driveway.

Type of Work: Replace existing 33'-6" AGL metal pole with new 39'-1" AGLE (38'-9" total) Valmont metal pole, installing new telecommunications equipment. See attached drawing for more details and scope of work.

Extent of closure: Partial lane closure, partial sidewalk closure. See page 19 of submitted drawing. Areas will be reopened for the evening once the crew completes for the day.

Expected date and/or duration: 9/8/2025-3/8/2026
Work is expected to take about 3 days to complete.
https://bloomington.in.gov/inroads/events/view?id=6589

-------------------------------------------------
## Crown Castle Small Cell Tower Work ##
902 E Cottage Grove Ave



September 15, 2025 to March 15, 2026
Lane Restriction; expect short delays, signage in place.
SC-IN E Cottage Grove Ave 522219_0204

Location: In the ROW to the north of the apartment complex at 900 E Cottage Grove Ave

Type of Work: Replace existing utility pole with new 50' wood utility pole (43'-0" final above grade height) and install telecommunications equipment. See attached drawing for more details and scope of work.

Extent of closure: Lane closure and detour, sidewalk closure. See page 16 of submitted drawing.

Expected date and/or duration: 9/15/2025-3/15/2026.
The work is expected to take 3 days max with the area being opened during the evening hours.
https://bloomington.in.gov/inroads/events/view?id=6585

-------------------------------------------------
## Duke Energy Pole Work ##
612 E Atwater Dr



September 15, 2025 to October 31, 2025
Lane Restriction; expect short delays, signage in place.
WO #45028886, 1-2 lane closure in the eastbound lane of Atwater Ave to replace overhead equipment on pole # 177-201 and installing new pole # MNI-12665.
https://bloomington.in.gov/inroads/events/view?id=5862

-------------------------------------------------
## Duke Energy Lane Closure ##
2610 E Moores Pk



September 15, 2025 to November 30, 2025
Lane Restriction; expect short delays, signage in place.
WO # 42544965, lane closure on Installing new pole # MNI-12564 along S Side of E Moores Pike. No overnight closure. Work should be completed in 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6269

-------------------------------------------------
## Duke Energy Alleyway Closure ##
409 S Walnut St



September 15, 2025 to November 30, 2025
Road Closed; expect to detour, signage in place.
WO # 42544967, Replacing pole # 152-907 in alleyway south of E Smith Avenue and West of S Walnut Street. No overnight closure. Work should only take 1 day, but please allow for 3 days in case of inclement weather.
https://bloomington.in.gov/inroads/events/view?id=6268

-------------------------------------------------
## Witch Fest ##
6th St between Walnut and College



September 20, 2025 06:00 am to 22:00 pm
Road Closed; expect to detour, signage in place.
Witch Fest (www.oak-bloomington.com/)
https://bloomington.in.gov/inroads/events/view?id=6624

-----------------------------------------------------------
To update your subscription status, please visit:
https://groups.google.com/forum/#!forum/cob_road_closings
Reply all
Reply to author
Forward
0 new messages