Road events for next week, 3/9/2026 to 3/16/2026:
########################################################
-------------------------------------------------
## Allen St. Bridge ##
Bridge between S Morton and S Walnut (150-156 W Allen St)
W Allen ST from S Morton ST to S Walnut ST
January 7, 2020 to January 7, 2027
Road Closed; expect to detour, signage in place.
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
https://bloomington.in.gov/inroads/events/view?id=3798
-------------------------------------------------
## Poplars Redevelopment ##
400 E 7th St
November 22, 2025 to June 18, 2026
Road Closed; expect to detour, signage in place.
Phase 3 of 4 of the Poplars redevelopment. Closures to be used for construction deliveries and material movement.
This phase includes:
Single day closure on the east side of Grant for scaffolding installation (11/13/25) and single day (TBD) for removal.
Bike lane closure from 11/22/25 to 3/2/26.
Closures of the southern sidewalk along E 7th and the east/west alley on the southern side of the property from 11/22/25 to June 18th, 2026.
https://bloomington.in.gov/inroads/events/view?id=6947
-------------------------------------------------
## Construction for 115 E Kirkwood Lofts ##
115 E Kirkwood Ave
January 28, 2026 to July 28, 2027
Road Closed; expect to detour, signage in place.
Genesis Construction is requesting a pedestrian diversion and intermittent closures, traffic lane shifts and intermittent lane closures, alley closures, and metered parking reservations associated with the project at 115 E Kirkwood Avenue. The request impacts the northern sidewalk on E Kirkwood, the north–south and east–west alleys surrounding 115 E Kirkwood, the east–west travel lanes on E Kirkwood, and the metered parking spaces along the north and south side of E Kirkwood.
https://bloomington.in.gov/inroads/events/view?id=7083
-------------------------------------------------
## Bloomington Convention Center Project Lane Restriction ##
302 S College Ave
February 13, 2026 to June 26, 2026
Lane Restriction; expect short delays, signage in place.
Immediately following phase 2 completion, a lane closure of the eastern southbound lane of College Ave is being requested. This request is to accommodate placement of pedestrian diversion for curb and sidewalk demolition and reconstruction. The traffic control would be in place from February 13th, 2026 through June 26th, 2026
https://bloomington.in.gov/inroads/events/view?id=7086
-------------------------------------------------
## Poplar Redevelopment ##
400 E 7th St
February 23, 2026 to July 27, 2026
Road Closed; expect to detour, signage in place.
Sidewalk closures, metered parking reservations, and alley closures surrounding the former Poplars Building located at 400 E 7th Street. The request includes the eastern sidewalk and adjacent parking lanes on N Dunn Street, the southern sidewalk on E 7th Street, and the east/west alley between E 6th Street and E 7th Street.
The requested closures are to accommodate completion of exterior façade work, including masonry cleaning and sealing, followed by sidewalk reconstruction and perimeter landscaping along the east side of the Poplars Building on Dunn Street.
Traffic control on N Dunn Street is proposed to be in place from February 23, 2026, through July 17, 2026. Traffic control on E 7th Street and within the east/west alley between E 6th Street and E 7th Street will remain in place through July 27, 2026, to support final site concrete work and landscaping associated with project completion. F.A. Wilhelm has supplied maintenance of traffic plans for all prop
https://bloomington.in.gov/inroads/events/view?id=7115
-------------------------------------------------
## Arlington Multifamily Project Lane Closures ##
1210 W Arlington Rd
March 2, 2026 to June 16, 2026
Lane Restriction; expect short delays, signage in place.
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025.
Mayer Najem has supplied maintenance of traffic plans for all work. As a condition of the issuance of the ROW permit they will also be required to post signage notifying the public about the lane shifts at least 3 weeks prior to closure implementation.
https://bloomington.in.gov/inroads/events/view?id=6994
-------------------------------------------------
## High St Multi-Use Path Tree Clearing ##
S High St between Moores Pike and 2nd St
S High ST from E Hillside DR to E 2nd ST
March 6, 2026 to April 15, 2026
Lane Restriction; expect short delays, signage in place.
Tree clearing will be happening along S High St between Moores Pike and 2nd St. Tree clearing is along the eastern side of the roadway. There will be lane closures with flagging for northbound traffic.
https://bloomington.in.gov/inroads/events/view?id=7136
-------------------------------------------------
## Arlington Multifamily Utility Work ##
1210 W Arlington
March 9, 2026 to June 16, 2026
Lane Restriction; expect short delays, signage in place.
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025.
https://bloomington.in.gov/inroads/events/view?id=7131
-------------------------------------------------
## ROW2026-02-2275 ##
1020 N Monroe
March 9, 2026 to March 16, 2026
Lane Restriction; expect short delays, signage in place.
Single lane closure with Flaggers
https://bloomington.in.gov/inroads/events/view?id=7137
-------------------------------------------------
## ROW2025-12-2172 ##
1805 N Monroe St.
March 9, 2026 to March 23, 2026
Lane Restriction; expect short delays, signage in place.
Single Lane closure 1 Day between dates.
https://bloomington.in.gov/inroads/events/view?id=7139
-------------------------------------------------
## CBU - Fire Hydrant Maintenance ##
North Elm Street will be closed to through traffic between West Kirkwood Avenue and West Sixth Street.
March 9, 2026 09:00 am to 15:00 pm
Road Closed; expect to detour, signage in place.
Crews will install the new hydrant, and no water service disruptions are anticipated during this phase. Motorists are encouraged to use alternate routes and remain alert for crews and equipment in the area.
https://bloomington.in.gov/inroads/events/view?id=7140
-------------------------------------------------
## CBU - Fire Hydrant Maintenance ##
Intersection of West Kirkwood Avenue and North Elm Street
March 9, 2026 22:00 pm to 04:00 am March 10, 2026
Lane Restriction; expect short delays, signage in place.
Crews will begin removing the existing hydrant at 10:00 p.m. During this phase, there will be a lane restriction on West Kirkwood Avenue.
https://bloomington.in.gov/inroads/events/view?id=7141
########################################################
Future road events
########################################################
-------------------------------------------------
## ROW2026-02-2310 ##
1100 E Miller
March 20, 2026 to March 27, 2026
Lane Restriction; expect short delays, signage in place.
Lane closure of Olive St.
https://bloomington.in.gov/inroads/events/view?id=7132
-----------------------------------------------------------
To update your subscription status, please visit: