Road events for next week, 1/12/2026 to 1/19/2026:
########################################################
-------------------------------------------------
## Allen St. Bridge ##
Bridge between S Morton and S Walnut (150-156 W Allen St)
W Allen ST from S Morton ST to S Walnut ST
January 7, 2020 to January 7, 2027
Road Closed; expect to detour, signage in place.
County closed bridge to motor vehicles until it can be replaced. Bridge will remain open for bicyclists and pedestrians.
https://bloomington.in.gov/inroads/events/view?id=3798
-------------------------------------------------
## Bloomington Convention Center Site Preparation ##
302 S Walnut st
June 27, 2025 to January 26, 2026
Lane Restriction; expect short delays, signage in place.
This request is to accommodate site work necessary for the Bloomington Convention Center Project. The traffic controls would be in place from June 27th, 2025 through January 23rd, 2026. Other permits for various closure needs are also expected between phase completions.
https://bloomington.in.gov/inroads/events/view?id=6556
-------------------------------------------------
## Crown Castle Small Cell Tower Work ##
1314 N Eagleson Ave
September 8, 2025 to March 8, 2026
Lane Restriction; expect short delays, signage in place.
SC-IN E 17th St 523288_0167
Location: In the ROW at the corner of E 17th St and the private driveway.
Type of Work: Replace existing 33'-6" AGL metal pole with new 39'-1" AGLE (38'-9" total) Valmont metal pole, installing new telecommunications equipment. See attached drawing for more details and scope of work.
Extent of closure: Partial lane closure, partial sidewalk closure. See page 19 of submitted drawing. Areas will be reopened for the evening once the crew completes for the day.
Expected date and/or duration: 9/8/2025-3/8/2026
Work is expected to take about 3 days to complete.
https://bloomington.in.gov/inroads/events/view?id=6589
-------------------------------------------------
## Crown Castle Small Cell Tower Work ##
902 E Cottage Grove Ave
September 15, 2025 to March 15, 2026
Lane Restriction; expect short delays, signage in place.
SC-IN E Cottage Grove Ave 522219_0204
Location: In the ROW to the north of the apartment complex at 900 E Cottage Grove Ave
Type of Work: Replace existing utility pole with new 50' wood utility pole (43'-0" final above grade height) and install telecommunications equipment. See attached drawing for more details and scope of work.
Extent of closure: Lane closure and detour, sidewalk closure. See page 16 of submitted drawing.
Expected date and/or duration: 9/15/2025-3/15/2026.
The work is expected to take 3 days max with the area being opened during the evening hours.
https://bloomington.in.gov/inroads/events/view?id=6585
-------------------------------------------------
## ROW2025-10-2024 ##
East-West alley North of 205 E Kirkwood AVE
November 8, 2025 to January 16, 2026
Road Closed; expect to detour, signage in place.
Alley closure for loading and unloading- along with parking spots.
https://bloomington.in.gov/inroads/events/view?id=6939
-------------------------------------------------
## Poplars Redevelopment ##
400 E 7th St
November 22, 2025 to March 2, 2026
Lane Restriction; expect short delays, signage in place.
Phase 3 of 4 of the Poplars redevelopment. Closures to be used for construction deliveries and material movement.
This phase includes:
Single day closure on the east side of Grant for scaffolding installation (11/13/25) and single day (TBD) for removal.
Bike lane closure from 11/22/25 to 3/2/26.
Closures of the southern sidewalk along E 7th and the east/west alley on the southern side of the property from 11/22/25 to June 18th, 2026.
https://bloomington.in.gov/inroads/events/view?id=6945
-------------------------------------------------
## Poplars Redevelopment ##
400 E 7th St
November 22, 2025 to June 18, 2026
Road Closed; expect to detour, signage in place.
Phase 3 of 4 of the Poplars redevelopment. Closures to be used for construction deliveries and material movement.
This phase includes:
Single day closure on the east side of Grant for scaffolding installation (11/13/25) and single day (TBD) for removal.
Bike lane closure from 11/22/25 to 3/2/26.
Closures of the southern sidewalk along E 7th and the east/west alley on the southern side of the property from 11/22/25 to June 18th, 2026.
https://bloomington.in.gov/inroads/events/view?id=6947
-------------------------------------------------
## SERVICE MASTER ##
200 E 5TH ST
December 31, 2025 to January 14, 2026
Road Closed; expect to detour, signage in place.
METERS 201A&B, 203A&B, 205A
https://bloomington.in.gov/inroads/events/view?id=7037
-------------------------------------------------
## ROW2025-11-2102 ##
1104 N Grant
January 7, 2026 to January 21, 2026
Road Closed; expect to detour, signage in place.
3 days of alley closure for DUKE
https://bloomington.in.gov/inroads/events/view?id=7039
-------------------------------------------------
## ROW2025-10-2022 ##
2744 S Pinehurst DR
January 12, 2026 to January 26, 2026
Lane Restriction; expect short delays, signage in place.
Closure of southbound lane of S Pinehurst for one day between 01/12/2026 and 01/26/2026
https://bloomington.in.gov/inroads/events/view?id=6869
-------------------------------------------------
## CBU - Stormwater Maintenance ##
N Old State Rd 37
January 12, 2026
Lane Restriction; expect short delays, signage in place.
CBU will be performing Stormwater Maintenance work on N Old State Rd 37, just south of the ball fields.
https://bloomington.in.gov/inroads/events/view?id=7045
########################################################
Future road events
########################################################
-------------------------------------------------
## Arlington Multifamily Project Lane Closures ##
1210 W Arlington Rd
March 2, 2026 to June 16, 2026
Lane Restriction; expect short delays, signage in place.
Mayer Najem is requesting lane shifts on W Arlington Rd adjacent to as part of the project located at 1320 W Arlington Rd. This request is for Sanitary sewer and storm upgrades, tapping water for the site, and transportation infrastructure updates totaling 7012 sq ft of non pavement and 7670 sq ft of pavement excavations. The traffic control is planned to be in place starting in early spring, currently estimated to be from March 2nd, 2026 through June 16th, 2025.
Mayer Najem has supplied maintenance of traffic plans for all work. As a condition of the issuance of the ROW permit they will also be required to post signage notifying the public about the lane shifts at least 3 weeks prior to closure implementation.
https://bloomington.in.gov/inroads/events/view?id=6994
-----------------------------------------------------------