MEDIANTE LA PRESENTE SE REMITE INFORME DE AVANCE DE OBRAS DEL PROYECTO DE CONSTRUCCIÓN DE RED DE DISTRIBUCIÓN DE AGUA POTABLE EN COMARCA CUAJACHILLO #2 Y TRINIDAD CENTRAL.

 