Re: [EXTERNAL] Re: FW: Ramp widths along Colfax BRT Project

33 views
Skip to first unread message

Bryan Wilson

unread,
May 27, 2026, 12:49:44 PMMay 27
to Colfax BRT, City Council District 10, frank, sociali...@gmail.com, Chris Nicholson, JoyAnn Ruscha, City Council District 5, Denver Moves Bikes, east-cent...@googlegroups.com, east-...@googlegroups.com, DOTI Sidewalks, City Council District 9, Procore Email (com-inbound-e-colfax-ave-brt-project-xcoirjqiah@us02.procoretech.com), City of Denver, on2w...@denver7.com, tips@kdvr.com EOC Media Partner COVID19 Response, Your City Your Voice, Hannah Metzger
Hello Colfax BRT Team,

I've done some more digging on this issue, which I think needs to be addressed...

If you refer to the Rules & Regulations Governing Encroachments to the Public Right-of-Way, raised encroachments are not to preclude the minimum standard Sidewalk width for adjacent street classification AND shall not obstruct stormwater drainage in and through the ROW nor cause water to collect on Sidewalks, streets or alleys.

15. Encroachments shall not preclude the minimum standard Sidewalk width for adjacent street classification.
19. Encroachments shall not obstruct stormwater drainage in and through the ROW nor cause water to collect on Sidewalks, streets or alleys or conflict with DRMC Section 49-554.

The "Adjacent Street Classification" is explained in the City of Denver Complete Streets Design Guidelines. Colfax is specifically called out as having a minimum width of 8ft. 

Generally, here's what I think all of this boils down to in no particular order of importance...
- Every raised curb along sidewalks needs to be removed to allow water to flow through the ROW freely. They should all look like the one currently being installed at Colfax & Steele, or at Colfax & Park Ave next to Scooter Liquors.
- Every sidewalk & ramp needs to be installed to 8ft wide or wider, unless something existed prior to the Rules & Regulations. So, with the exception of previously existing buildings, or large mature trees, any new encroachments to the public right-of-way should not be installed that preclude the minimum width of 8ft. One huge issue is the installation of all the beg-buttons at nearly EVERY intersection... We should program the signals to automatically cycle to a pedestrian phase & remove every beg-button along Colfax so that it functions much in the same way as 16th Street.

This has nothing to do with "public input," but restrictions that should have been placed on the project from the beginning, which were somehow omitted. These somehow all seem to apply to redevelopments, & need to apply to the Colfax BRT Project as well.

Please address these going forward & correct the issues that have been installed.

Respectfully,
Bryan Wilson


On Wed, Apr 22, 2026 at 12:29 PM Colfax BRT <colf...@denvergov.org> wrote:

Dear Bryan,

Thank you for your interest in the East Colfax BRT project.  

 

Final design of the project concluded in 2024, and construction is currently underway. The time for public input on design has ended, and the project is not accepting altered design suggestions. Additional information related to your concerns is outlined below. To review the final designs in full, please visit the project website.  

 

DOTI adheres to PROWAG (Public Right-of-Way Accessibility Guidelines), which dictates the alteration of facilities within the public right-of-way to maintain accessibility for use (pedestrian push buttons for crossing) and accessible circulation. The minimum widths for sidewalks can be found here. The regulation states “sidewalks constructed adjoining existing curbs shall be a minimum of five (5) feet wide measured from the back of the curb head, with expansion joint between sidewalk and curb, unless otherwise specified by the Engineer.”  

 

All project installations meet all PROWAG requirements and conflict clearances. The project design has been diligently reviewed and approved by the FTA and meets all ADA requirements. New light pole and equipment installations have been specifically placed to meet all design standards and requirements while also avoiding underground utility conflicts. The above ground installations you have identified through emails and social media have been installed correctly and legally with a multitude of review processes and will not be altered. 

 

At the corner of Williams Street and Colfax Ave, there will be trees installed. You can view the final design in more detail here

The project worked closely with DOTI’s bike planners to incorporate several bikeway connections across Colfax as part of the BRT project. Reach out to the city’s bike team to discuss your concerns about bikeway plans and connections with the Denver Bike Team at bi...@denvergov.org. You can also share specific Denver Moves: Bikes project feedback by emailing denve...@denvergov.org or calling (720) 865-9378.  

 

Unfortunately, we are unable to add Google groups to our mailing list due to limitations with our mass mailing software. We apologize for the inconvenience. You may be able to automatically forward our email updates to your Google group through your email provider.  

 

While no project of this magnitude can satisfy everyone, the goals of the project are to create a more reliable, sustainable and safe experience for all people who move throughout the corridor. We appreciate your enthusiasm for public transit and bikeways that support meaningful connections and movement for all community members.  

 

Thank you, 

East Colfax BRT Project Team 

 

 

From: Bryan Wilson <bryan...@gmail.com>
Sent: Monday, March 2, 2026 6:11 AM
To: City Council District 10 <Distr...@denvergov.org>; frank <fr...@colfaxave.com>; sociali...@gmail.com
Cc: Chris Nicholson <Chris.N...@rtd-denver.com>; JoyAnn Ruscha <JoyAnn...@rtd-denver.com>; City Council District 5 <DenverC...@denvergov.org>; Denver Moves Bikes <bi...@denvergov.org>; east-cent...@googlegroups.com; east-...@googlegroups.com; Colfax BRT <colf...@denvergov.org>; DOTI Sidewalks <Side...@denvergov.org>; Haines, Amber <amber....@atkinsrealis.com>; City Council District 9 <Dist...@denvergov.org>
Subject: [EXTERNAL] Re: FW: Ramp widths along Colfax BRT Project

 

Hello again, I'm now asking for my city council member and the local business improvement districts to see if they can find the answers to these questions... Why aren't we prioritizing 8-ft wide sidewalks along Colfax? Why are we installing

Hello again, 

 

I'm now asking for my city council member and the local business improvement districts to see if they can find the answers to these questions...

 

Why aren't we prioritizing 8-ft wide sidewalks along Colfax? 

Why are we installing signal posts and what seems to clearly be the Pedestrian access route?

 

I do understand budget constraints and why we can't widen every sidewalk, but I feel we can and should be installing 8-ft wide sidewalk ramps as often as possible. 

 

Instead, we're installing new signal posts that result in sidewalk ramps that are incredibly narrow, especially at Transit stations. 

 

 

I'm also concerned about the raised curbs being installed along sidewalks. 

 

Thank you in advance for your help!

 

Respectfully,

Bryan Wilson 

 

On Tue, Feb 10, 2026, 10:01AM Bryan Wilson <bryan...@gmail.com> wrote:

Hello again, Amber.

 

I just wanted to see if you had a chance to locate the documentation about the minimum sidewalk requirements. 

 

I agree that they broadly state a minimum of 5 ft, but that minimum I think is different as the street types move up from residential to collector to arterial.

Just walked past Colfax at Williams, where I feel it's clear that we could have achieved an 8-ft wide ramp even if it wasn't required.

 

I also believed the raised curbs shouldn't be installed when reviewing the rules and regulations governing encroachments to the public right of way. 

It's my understanding that these are not to obstruct water from flowing off the sidewalk into the tree lawn because it'll result in ice melt refreezing on the sidewalk. 

 

 

I'll have to see if I can find the answer to my sidewalk question there. 

 

Thank you in advance for your help! 

 

Respectfully,

Bryan Wilson 

 

 

On Mon, Jan 26, 2026, 11:42AM Bryan Wilson <bryan...@gmail.com> wrote:

Thank you for the response, Amber.

Can you please clarify the "must-have" widths & where that is documented?
I've observed a number of developments upgrading to 8ft wide, so I find it hard to believe that they would spend extra money unnecessarily when it isn't required of them.
 - South side of Colfax from Downing to Marion
 - North side of Colfax from Milwaukee to Saint Paul
 - South side of Colfax from Madison to Monroe
 - North side of Colfax from Monroe to Garfield
 - South side of Colfax from Garfield to Harrison
Just seems like there is one standard for developers & another for this project. 

 
As for the signals, they're being relocated at many other intersections. Why can't they be relocated at these other locations the same way?
I just watched the signals get relocated on Colfax at Williams. Will we get 8ft wide ramps there?


I don't understand why 8ft wide widths seem to be prioritized for redevelopments, but not for this project.

Thank you in advance for your help!

Respectfully,
Bryan Wilson



 

On Mon, Jan 26, 2026 at 10:57AM Haines, Amber <Amber....@atkinsrealis.com> wrote:

Hi Bryan,

 

In response to your below inquiry, the design team followed the CCD standards for the “must have” widths. We did take the Complete Streets guidelines into consideration for the “where possible” widths, and DOTI committed to placing 8’ widths where we do not have above or below ground built condition conflicts.  This specific location at Colfax/Vine Street has a signal and equipment preventing us from upsizing to the 8’ width.

 

Thanks,

 

Amber Haines  

East Colfax Ave BRT

Tel: 970.389.1779  

 

 

 


From: Bryan Wilson <bryan...@gmail.com>
Sent: Saturday, January 17, 2026 12:35 PM
To: City Council District 10 <
distr...@denvergov.org>; Chris Nicholson <Chris.N...@rtd-denver.com>; JoyAnn Ruscha <JoyAnn...@rtd-denver.com>; City Council District 5 <DenverC...@denvergov.org>
Cc: Denver Moves Bikes <
bi...@denvergov.org>; east-cent...@googlegroups.com <east-cent...@googlegroups.com>; east-...@googlegroups.com <east-...@googlegroups.com>; Colfax BRT <colf...@denvergov.org>
Subject: Ramp widths along Colfax BRT Project

 

Hello Council members Hinds & Sawyer, and RTD Directors Nicholson & Rusha,

 

Could you please connect with the Colfax BRT Project team to find out why we're not installing 8ft wide sidewalk ramps at intersections where there is sufficient space?

 

Here is an example at Colfax & Vine.


 

The Right-of-Way is clearly marked to the right indicating that there is plenty of space to accommodate a wider ramp. It's my understanding based on the Complete Streets Guidelines that the sidewalk & ramps along Colfax should be a minimum of 8ft wide, but wider where possible.

https://www.denvergov.org/files/assets/public/v/2/doti/documents/standards/doties-017.0_complete_streets_guidelines.pdf

 

At other locations, like at City Park Esplanade, we could probably be installing 12ft wide ramps & designating it as a shared-use connection to the Josephine & York Street Stations.

https://www.instagram.com/reel/DTnzbAikbwt/?igsh=NHllaWZvZ3RpajFi

 

I requested that in the prior email below.

 

Obviously, we won't be able to do that where buildings are in the way, but that isn't the case with Vine Street & other locations.

 

Thank you in advance for your help!

Please respond when you're able to get any information.

 

Respectfully,

Bryan Wilson 

 

 

 

On Tue, Jan 6, 2026, 10:53AM Bryan Wilson <bryan...@gmail.com> wrote:

Hello,

 

Please reference the Denver Moves Bikes Update and the plans for the Colfax BRT project.

 

Requesting both to be updated identifying the sidewalk along Colfax Ave between York and Detroit Street as shared-use. 


https://storymaps.arcgis.com/stories/f4fafe1405b6443da158f4d9e257887a

ColfaxBRT.org


I added the sections in question with the yellow dots.

 

This will not only connect riders from the Colfax BRT transit station to the Carla Madison Rec Center, but also connect riders from the Carla Madison Rec Center to the future 16th Avenue neighborhood Bikeway to the East of Denver East High School.

 

This would be an excellent opportunity for the Colfax BRT project to install wider sidewalk ramps to accommodate Shared-use.

 

Thank you in advance for your help! 

 

Respectfully,

Bryan Wilson 

 

 

NOTICE – This email message and any attachments may contain information or material that is confidential, privileged, and/or subject to copyright or other rights. Any unauthorized viewing, disclosure, retransmission, dissemination, or other use of or reliance on this message or anything contained therein is strictly prohibited and may be unlawful. If you believe you may have received this message in error, kindly inform the sender by return email and delete this message from your system. Thank you.

Reply all
Reply to author
Forward
0 new messages