組織已經完成關鍵業務的業務流程再造(BPR), IS審計師最有可能的審查重點:
A.BPR實施前的流程圖
B.BPR實施後的流程圖
C.BPR專案計劃
D.持續改進和監測計劃
Q582. Once an organization has finished the business process
reengineering (BPR) of all its critical operations, the IS auditor
would MOST likely focus on a review of:
A. pre-BPR process flowcharts.
B. post-BPR process flowcharts.
C. BPR project plans.
D. continuous improvement and monitoring plans.
2002的說明
Answer: A. pre-BPR process flowcharts.
Explan: The IS auditor's task is to identify the existing key controls
from the pre-BPR processes and determine if these controls still exist
in the new processes.
2010的說明
Answer: B
Note: An IS auditor's task is to identify and ensure that key controls
have been incorporated into the reengineered process. Choice A is
incorrect because an IS auditor must review the process as it is
today, not as it was in the past.