Shall we meet on 20-7-2014

10 views
Skip to first unread message

Rathakrishnan M

unread,
Jul 6, 2014, 9:43:42 AM7/6/14
to chaitra_...@googlegroups.com, chaitrasheltersblr
Dear All,
 
Let us discuss about our layout current status on next-but-next sunday.
 
Happenings in & around our layout.
  1. 3 houses are in completed state. owners already took possession.
  2. 2 houses are in construction phase.
  3. 1 house is in ready to occupy state. Owner is taking possession on coming week.
  4. Some portion of our layout-compound-wall has fallen due to last rains.
  5. BBMP started dumping garbages again, back to our layout.
  6. Prestige apartment construction goes in full swing.
  7. A new layout is formed next to our layout.

Our Layout developer will be joining us in this meeting.  Other topics & issues Will be on coming mails.. Stay tuned..

 
Regards
Rathakrishnan.M

Tousif Sayed

unread,
Jul 6, 2014, 1:03:39 PM7/6/14
to Rathakrishnan M, chaitra_...@googlegroups.com, chaitrasheltersblr
Hi,
Two most important things for me from Phase -2 perspective,
1.Electricity for phase-2 : Transformer is not put even after several appeals to the seller.There are no street lights in phase-2.
2.Bore well for phase-2 : Phase -2 gets very little water due to proximity of bore well to phase-1 and as house are being built in phase-1 the shortage of water will only increase for phase-2.Need bore well for phase-2 and this will balance out the flow of water and every one in layout will have sufficient water.

Regards
Tousif



Rathakrishnan.M

--
You received this message because you are subscribed to the Google Groups "Chaitra Shelters" group.
To unsubscribe from this group and stop receiving emails from it, send an email to chaitra_shelte...@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

Chinthu Harshan

unread,
Jul 9, 2014, 11:56:28 PM7/9/14
to chaitrash...@googlegroups.com, chaitra_...@googlegroups.com, Rathakrishnan M

Hi All,
Found the following news in today' Hi du(image attached) about Khata.
Will we be eligible for it?
Also What about creating a whatsapp group for chaitra shelters?

You received this message because you are subscribed to the Google Groups "ChaitraSheltersBLR" group.
To unsubscribe from this group and stop receiving emails from it, send an email to chaitrashelters...@googlegroups.com.
2014-07-10_08-55-45_850.jpg

Vangala Madhusudhan Reddy

unread,
Jul 12, 2014, 10:05:14 AM7/12/14
to Chinthu Harshan, chaitrash...@googlegroups.com, chaitra_...@googlegroups.com, Rathakrishnan M
Hi All, 

I have raised a concern regarding garbage deposition next to our layout. Please vote that you are affected with the issue.  

I have seen some of the issue were resolved. Not sure if our issue gets resolved or not but it's a try. 

Regards
Madhu 

Best Regards
Madhu

Ramaiya

unread,
Jul 13, 2014, 10:31:08 PM7/13/14
to Vangala Madhusudhan Reddy, Chinthu Harshan, chaitrasheltersblr, chaitra_...@googlegroups.com, Rathakrishnan M
Team,

Please support the initiative taken by Madhu as it impacts us all.

Priyesh

Ganesh B

unread,
Jul 13, 2014, 11:41:57 PM7/13/14
to Ramaiya, Vangala Madhusudhan Reddy, Chinthu Harshan, chaitrasheltersblr, chaitra_...@googlegroups.com, Rathakrishnan M
Hi all,

I have voted for it. Are we meeting on 20/07?

Regards,
Ganesh

Madhu

unread,
Jul 15, 2014, 5:05:00 AM7/15/14
to Ganesh B, Ramaiya, Chinthu Harshan, chaitrasheltersblr, chaitra_...@googlegroups.com, Rathakrishnan M

Hi All,

Based on the complaint made in ichangemycity.com got a call from BBMP engineer. As per engineer we need to seize the vehicle's who is dumping garbage and inform them. Then BBMP would take action.

The above option will not work due to security reasons as there are fewer residents staying in layout and the person who took contract to dump garbage is with criminal background.

We need to go through Venkatesh Reddy who has some influence. If we are having meeting on 20th July it would be fruitful if  Venkatesh Reddy also present. Also everyone try to reach him if he can do something

Regards
Madhu


Sent from Windows phone

From: Ganesh B
Sent: ‎14-‎07-‎2014 09:11
To: Ramaiya
Cc: Vangala Madhusudhan Reddy; Chinthu Harshan; chaitrasheltersblr; chaitra_...@googlegroups.com; Rathakrishnan M
Subject: Re: Shall we meet on 20-7-2014

Madhu

unread,
Jul 16, 2014, 11:37:12 AM7/16/14
to chaitrash...@googlegroups.com, chaitra_...@googlegroups.com
Hi All, 

Complaint in Ichangemycity is assigned to BBMP engineer, but he is comfortable only with Kannada. Can anyone who can speak in Kannada call up the and explain our problem and how we can resolve this issue.  Below is the status in  Ichangemycity website.

"Your complaint has been assigned to sundrayya via Docket No: 153220. He / She can be reached on 9481904440. Please get in touch with him / her for resolving the complaint and change the status to Resolved once done."

Regards
Madhu

Rathakrishnan M

unread,
Jul 16, 2014, 1:35:16 PM7/16/14
to Chinthu Harshan, chaitrasheltersblr, chaitra_...@googlegroups.com
In my opinion, our layout is already eligible to get A-Khatha before to this announcement.

regards
Rathakrishnan.



On Thu, Jul 10, 2014 at 9:26 AM, Chinthu Harshan <toch...@gmail.com> wrote:

Rathakrishnan M

unread,
Jul 16, 2014, 1:41:48 PM7/16/14
to chaitrasheltersblr, Ganesh B, Ramaiya, Chinthu Harshan, chaitra_...@googlegroups.com
Very good initiative. Localities can take up this issue to next level.

regards
Rathakrishnan

Ramaiya

unread,
Jul 16, 2014, 10:56:41 PM7/16/14
to Rathakrishnan M, chaitrasheltersblr, Ganesh B, Chinthu Harshan, chaitra_...@googlegroups.com
Team,

This initiative will strengthen if we all make effort on our part.

I strongly recommend we all support the complain via visiting the site sent by Madhu

Please forward to other residents to sign up.

Priyesh

Rathakrishnan M

unread,
Jul 16, 2014, 11:39:24 PM7/16/14
to Tousif Sayed, chaitra_...@googlegroups.com, chaitrasheltersblr
Dear All,

No doubt. Points that Tousif mentioned is very well valid. That should be in first priority.
In addition to that,  I listed the pending activities below which needs to be discussed to prioritize:

Pending activities from Association:
1.Apply for A-Khatha (Chinthu already started this topic)
2.Task force Management
3.Collection of maintenance charges
4.Layout cleaning
5.Notice board @ entrance

Pending activties from developer:
1.Rs.40000 towards Electricity bills
2.Channel for drainage
3.STP
4.Handover layout original documents
5.Temple in Layout

New activities:
1.Renovation of compound wall
2.Installation of side gates adjacent to our main gate
3.Paint the main gate and other iron rods in the compound wall
4.Street light repair.

regards
Rathakrishnan.

Chandrasekharan Nair

unread,
Jul 17, 2014, 12:36:54 AM7/17/14
to Rathakrishnan M, Tousif Sayed, chaitra_...@googlegroups.com, chaitrasheltersblr

Dear All,

Agree with u.
I've not paid my maintenance charges for a long time as I've been traveling. Can somebody kindly let me know the pending amount? Site No. 14 in II phase in the name of Bindhu Menon.
--
Regards,

Chandrasekharan
Chief Coordinator
6th World Ayurveda Congress & AROGYA Expo, New Delhi

 Follow us:    

World's Largest Ayurveda Congress!
Over 5000 delegates
Participation from over 35 countries

Catch the excitement of 6th World Ayurveda Congress & AROGYA Expo at the world class exhibition center at Pragati Maidan, New Delhi, India from 6th to 9th November 2014!


"Print this mail only if absolutely necessary. Save Paper. Save Trees. Save Earth. Stay Green - Stay Cool"





Tousif Sayed

unread,
Jul 18, 2014, 2:49:30 AM7/18/14
to Rathakrishnan M, chaitra_...@googlegroups.com, chaitrasheltersblr
Hi,
Looking at the activities list I have a suggestion.If we compare our layout with others we do not have a garden/park/play ground in our layout.As per the A Khata rules the layout gets a A khata only if they have some space allocated for garden and hence many of us living in rented houses would have seen park in our colony or layout. So I believe our developer would have shown some plot for this purpose.So my suggestion is if at all if there is any vacant space or plots in our layout which will be handed to association then we should use it for generic purposes which can be used by all members of layout like say Association Office,Park, Garden etc based on the dimension of land.
Regards
Tousif

Vasantha Raju

unread,
Jul 18, 2014, 3:12:02 AM7/18/14
to Tousif Sayed, chaitra_...@googlegroups.com, chaitrasheltersblr, Rathakrishnan M

All,

I request each of you to call the developer & ask him to come for the meeting without fail. Otherwise the meeting is not going to help.

Regards
Vasanth

Vangala Madhusudhan Reddy

unread,
Jul 29, 2014, 11:35:03 PM7/29/14
to Pampapathi U B (RBEI/EBA1), chaitrash...@googlegroups.com, chaitra_...@googlegroups.com
Hi Pampapathi, 

Thanks for coming forward. Below is the BBMP engineer to which issue is assigned with his mobile number. Can you reach out him and explain the issue we are facing because of the dump and solution to stop the dump. May be you can explain him that we would not be able to seize vehicles because of security reasons. If govt/BBMP place notice board at least we can resist to some extent showing that board.  


Your complaint has been assigned to sundrayya via Docket No: 153220. He / She can be reached on 9481904440. Please get in touch with him / her for resolving the complaint and change the status to Resolved once done.

Dear Association, 
Individual may not be able to take this issue forward, as an association we should approach BBMP. Resolving issues would also gain confidence of every member in the layout and helps in better collection of dues which in turn help our layout a better place for living. If required we can give police complaint. 

Dear Members, 
Please try to contact Venaktesh reddy or his brother and highlight all the issues we have for which he is responsible. 

If Garbage is not going to stop in another 2 or 3 month we would not be able stay here because various issue due to dump. 

Thanks
Madhu      


On Fri, Jul 18, 2014 at 12:54 PM, Pampapathi U B (RBEI/EBA1) <Pampap...@in.bosch.com> wrote:

I can volunteer for this as I am from Karnataka and fluent in Kannada

You can reach me at  : 9741211448

 

Mit freundlichen Grüßen / Best regards

 

Pampapathi U B

RBEI/EBA

 

Tel. +91 80 4109 5861

Fax +91 80 4191 0

Signature_image_o

 

From: chaitrash...@googlegroups.com [mailto:chaitrash...@googlegroups.com] On Behalf Of Madhu
Sent: Wednesday, July 16, 2014 9:07 PM
To: chaitrash...@googlegroups.com
Cc: chaitra_...@googlegroups.com


Subject: Re: Shall we meet on 20-7-2014

 

Hi All, 

--
You received this message because you are subscribed to the Google Groups "ChaitraSheltersBLR" group.
To unsubscribe from this group and stop receiving emails from it, send an email to chaitrashelters...@googlegroups.com.


For more options, visit https://groups.google.com/d/optout.




--
Best Regards
Madhu

Ramaiya

unread,
Jul 30, 2014, 12:48:46 AM7/30/14
to Vangala Madhusudhan Reddy, Pampapathi U B (RBEI/EBA1), chaitra_...@googlegroups.com, chaitrash...@googlegroups.com

Just a thought. Have we tried reaching out to prestige who is building next to our layout? I am sure it impacts their customers too. Priyesh

You received this message because you are subscribed to the Google Groups "Chaitra Shelters" group.
To unsubscribe from this group and stop receiving emails from it, send an email to chaitra_shelte...@googlegroups.com.
Reply all
Reply to author
Forward
0 new messages