ajinky...@yahoo.com saw this article on ePaper Edition : The Times of India - Pune Dated: 25 Oct 2015 ePaper, and thought you would find it interesting.
You can find it at: - Chip in with views for Pimpri Chinchwad%27s developmentI feel we can utilise this opportunity for pushing our demand for expediting the issue of pending roadsconnecting our society.Let us all post suggestions in the PCMC website for :1. Connecting road from Hinjewadi Road (near IOC petrol pump) through survey no. 62/1 to wakadkar wasti road and2. widening of Wakadkar wasti road.Regards,Ajinkya Koli, B1 - 1002On Tuesday, October 13, 2015 7:22 PM, Vijayshree Patil <vijay...@gmail.com> wrote:
Thanks Ajinkya,I want to have this meeting as early as possible as I am going out of India for six months. Kindly arrange this meeting.Regards,Vijayshree PatilOn Tue, Oct 13, 2015 at 5:04 PM, KOLI AJINKYA <ajinky...@yahoo.com> wrote:On Tuesday, October 13, 2015 4:55 PM, KOLI AJINKYA <ajinky...@yahoo.com> wrote:
Dear Sir,In the last meeting (which was called at a very short notice) with one of the Directors of Aum Sanskruti, various issues were discussed. Due to the short notice, very few residents could attend the meeting. It had ended on a note that Aum Sanskruti Management will very soon call a meeting to apprise the residents about the pending issues.All of us are waiting to be updated about all the issues and therefore request that a meeting should be convened at the earliest, preferably in first half of this Saturday, 17th October, 2015 with Directors. Many owners are staying outside and they have expressed wish to attend the meeting. We therefore request you to convey the exact date and time of the meeting at the earliest.Regards,On Behalf of CASA IMPERIA B WINGOn Monday, August 31, 2015 5:35 PM, Dhananjay Jain <jain.dha...@gmail.com> wrote:
Yes Sir,Very soon we will start. give me a couple of days time .Regards,Amit SinhaOn Mon, Aug 31, 2015 at 4:56 PM, Ajinkya Koli <ajinky...@yahoo.com> wrote:Dear Sir,We hope that Mr. Alpesh Patel has recovered by now.
We are waiting for replies to our queries and all pending issues.Ajinkya Koli
9769588455On 20-Aug-2015 1:09 pm, Dhananjay Jain <jain.dha...@gmail.com> wrote:Dear All,Mr. Alpesh Patel is not well so kindly have patience we will get back very soon.Regards,Amit SinhaOn Thu, Aug 20, 2015 at 11:33 AM, Ajinkya Koli <ajinky...@yahoo.com> wrote:Dear Sir,
We request you to expedite resolution of all the pending issues:
1. Car Parking allotment is a major issue now as occupancy has increased. It should be done without any further delay.
2. We should be intimated as to what amenities will be provided as we have been getting different versions verbally. We would be glad if complete plan of amenities (showing its proposed location and dimensions) is shared with everyone.
3. We were verbally informed that final inspection has been done by Top Official of PCMC. So kindly appraise us of latest status of OC.
Thanks n Regards,
Ajinkya Koli
9769588455
---------- Forwarded message ----------
From: deepali shirali <deepali...@hotmail.com>
Date: 20-Aug-2015 10:39 am
Subject: RE: ISSUES OF CASA IMPERIA B WING
To: Dhananjay Jain <jain.dha...@gmail.com>
Cc: KOLI AJINKYA <ajinky...@yahoo.com>,Bhushan Tipnis <bti...@gmail.com>," roh...@yahoo.com" <roh...@yahoo.com>,"anja...@rediffmail.com " <anja...@rediffmail.com>,Rashmi Kulkarni <rashm...@gmail.com>,abhijit mhase <abhi....@gmail.com>,"manges...@gmail.com " <manges...@gmail.com>,saurabh agrawal <saurabh.a...@gmail.com>,Sachin A <sachin...@gmail.com>,sarala joshi <joshi.s...@gmail.com>,Anup Shirolkar <anupsh...@gmail.com>,sunil bramhe <sunilk...@gmail.com>,Somesh Bhalerao <somesh....@gmail.com>," nsb...@yahoo.com" <nsb...@yahoo.com>,"shriniva...@gmail.com " <shriniva...@gmail.com>,"dhawalc...@ymail.com " <dhawalc...@ymail.com>,jobha...@gmail.com,K J Phadke <k.j.p...@gmail.com>,Abhijeet Bedare <abhijee...@gmail.com>,Pratik Balakrishnan <pratik...@gmail.com>,Manish Suri <manish...@gmail.com>,pat...@yahoo.com," ven...@yahoo.com" <ven...@yahoo.com>,Gaurav Kale <ggk...@gmail.com>," prasad.g...@gmail.com" <prasad.g...@gmail.com>,Avanish Chaturvedi <avanis...@gmail.com>,Rajesh Thite <thite...@gmail.com>," milind_h...@yahoo.co.in" <milind_h...@yahoo.co.in>,aditya madkekar <aditya....@gmail.com>,Vijayshree Patil <vijay...@gmail.com>,htal...@gmail.com,Ramchandra Narkhede <ramchandr...@gmail.com>,Jayesh Bhave <jjb...@gmail.com>
> dhananjay,
> It's nearly August 2015 end, when is the final OC coming in and what exactly is holding it up?
> If i had known this project is going to get into such a loop i would have never invested in it.
>
> This is getting ridiculous, we need answers now!
>
> rgds
> deepali shirali
>
>
>
> ________________________________
> Date: Wed, 19 Aug 2015 21:41:06 +0530
> Subject: Re: ISSUES OF CASA IMPERIA B WING
> From: jjb...@gmail.com
> To: ramchandr...@gmail.com
> CC: jain.dha...@gmail.com; ajinky...@yahoo.com; bti...@gmail.com; roh...@yahoo.com; anja...@rediffmail.com; rashm...@gmail.com; abhi....@gmail.com; manges...@gmail.com; saurabh.a...@gmail.com; sachin...@gmail.com; joshi.s...@gmail.com; deepali...@hotmail.com; anupsh...@gmail.com; sunilk...@gmail.com; somesh....@gmail.com; nsb...@yahoo.com; shriniva...@gmail.com; dhawalc...@ymail.com; jobha...@gmail.com; k.j.p...@gmail.com; abhijee...@gmail.com; pratik...@gmail.com; manish...@gmail.com; pat...@yahoo.com; ven...@yahoo.com; ggk...@gmail.com; prasad.g...@gmail.com; avanis...@gmail.com; thite...@gmail.com; milind_h...@yahoo.co.in; aditya....@gmail.com; vijay...@gmail.com; htal...@gmail.com
>
> All the points mentioned in mail are vital and important. The possession started in Feb 2015 (may be before) with assurance of OC will be available within few days. What is the update? How builder is chasing with authorities? Why they are holding the OC?
>
> You have charged the maintenance for the entire facility including amenities. Almost 6 months have passed, there shall be firm commitment from Dhananjay to fulfil in totality. There shall be some kind check if commitments are not met.
>
> best regards
>
> On Wed, Aug 19, 2015 at 12:03 PM, Ramchandra Narkhede <ramchandr...@gmail.com> wrote:
>>
>> Dhananjay,
>>
>> What about parking allotment? 10-15 Aug is already gone. What is the problem now for?
>>
>>
>> - Ramchandra
>>
>>
>> On Wed, Jul 29, 2015 at 12:08 PM, KOLI AJINKYA <ajinky...@yahoo.com> wrote:
>>>
>>> FORWARDED FOR INFORMATION OF ALL RESIDENTS WHO MAY HAVE MISSED WHATSAPP
>>> CONVERSATIONS.
>>>
>>> THEREAFTER A MEETING WITH ONE OF THE SENIOR REPRESENTATIVE OF BUILDERS
>>> WAS CONDUCTED ON 25.07.2015
>>>
>>>
>>>
>>> -------- Forwarded Message --------
>>> Subject: Re: CASA IMPERIA B WING - MEETING DT. 19.07.2015
>>> Date: Fri, 24 Jul 2015 16:46:56 +0530
>>> From: AJINKYA KOLI <aji...@sbp.co.in>
>>> To: Dhananjay Jain <jain.dha...@gmail.com>
>>> CC: aumg...@yahoo.com, manish...@gmail.com, mech.nil...@gmail.com
>>>
>>> Dear Sir,
>>>
>>> We Thank you for your prompt point-wise response.
>>>
>>> All these points were put up to the residents in the stand-in meeting of residents held in the late evening
>>> of 23.07.2015.
>>>
>>> All the residents have expressed deep concern about point #1 i.e. temporary approach road issue,
>>> due to which provision of main amenities viz. Club House and swimming pool have been hampered. We are
>>> afraid that there will be an inordinate delay in these amenities, which is not acceptable.
>>> As such, Residents want to escalate this very important issue directly with Directors of Aum Sanskruti Housing.
>>>
>>> We request you to arrange an urgent meeting with the Directors preferably on Saturday, 25.07.2015 Morning.
>>>
>>> Regards,
>>>
>>> CASA IMPERIA "B' BUILDING RESIDENTS.
>>> ============================================================================
>>>
>>> On 7/23/2015 5:55 PM, Dhananjay Jain wrote:
>>> Hi Sir,
>>>
>>> Please below reply on the point which has discussed in the meeting.
>>>
>>> Point 1 : Point discussed and we tried our level best about this but practically looking all the aspects this is not possible as of now.
>>>
>>> Point 2 : Meeting have held with security guard dated on 27/07/2015, Please let us know your suitable time.
>>>
>>> Point 3 : Parking allotment will start from 10/08/2015.
>>>
>>> Point 4 : Not Committed and not possible now.
>>>
>>> Point 5 : Solar will start operating by 30/07/2015.
>>>
>>> Point 6 : Notice board will be fixed 30/07/2015 and keys for letter box will be handover dated on 28/07/2015.
>>>
>>> Point 7 : Speed breaker paint will be done before 30/07/2015
>>>
>>> Point 8 : We are searching good vendor, you also let us know if any good option is there will get resolve as soon as possible.
>>>
>>> Point 9 : Already CC TV camera placed in such a way to cover surrounding of the premises.
>>>
>>> Point 10 : Will discuss individually.
>>>
>>> Point 11 : Very soon we will put boom barrier with security cabin.
>>>
>>> Point 12 : Detail of fund will be provide with reciept at the time of handover.
>>>
>>>
>>> Regards,
>>> Dhananjay Jain
>>> ===============================================================================
>>> -------- Forwarded Message --------
>>> Subject: CASA IMPERIA B WING - MEETING DT. 19.07.2015
>>> Date: Mon, 20 Jul 2015 16:32:26 +0530
>>> From: AJINKYA KOLI <aji...@sbp.co.in>
>>> To: jain.dha...@gmail.com
>>>
>>> Dear Sir,
>>>
>>> A meeting of CASA IMPERIA ‘B’ Wing residents was held on Sunday, 19th August, 2015 with Shri Dhananjay Jain of Aum Sanskruti Developers to discuss very important and urgent issues being faced by residents. As earlier, only verbal assurances and varied time frames were being given by different representatives of Builders, it was decided to put forth all the issues in writing and Sh. Dhananjay Jain has agreed to respond them point-wise within a specific time frame.
>>>
>>> 1. Proper Entrance gate and proposed boundary wall for B Building should be erected. Presently, the space earmarked for amenities for B wing residents, is being used as approach road for A wing residents. Due to this construction of all the amenities has been held up and has resulted in an inordinate delay. We have suggested to that alternatively, A wing residents can use road going through the “gaothan” in front side of complex.
>>>
>>> D.J.: He will be discussing the chronic issue with A Building residents and local villagers to allow use of the road. He will update the status latest by 26th July, 2015.
>>> 2. Security is a major concern area as security personnel are inadequate and not trained. No security guards are present at night.
>>> D.J. : He will be arranging meeting with chief of security agency in forthcoming week and the requirement of security persons will be arrived at with concurrence of residents. Meeting scheduled not later than 22nd July, 2015.
>>> 3. Car parking allotment has been over-delayed and strong resentment for the same was conveyed. It is causing lot of inconvenience to all residents.
>>> D.J. : Car parking allotment decision will be taken by Saturday, 25th July, 2015.
>>>
>>> 4. A need for an Intercom System was felt by residents which can also be useful from security point of view. As such, request for installation of good Intercom system was made by all residents.
>>> D.J. : The request for Intercom System will be conveyed to the Management and the decision regarding the same will be taken by 25th July, 2015.
>>>
>>> 5. Solar Heating system though installed is not operational till date. In view of change of season, the need for the same has arisen. Also since more than 70 % flats have been occupied, it is now feasible to make this amenity functional.
>>> D.J. : He did not envisage any issue in commencing the operation, so he will be conveying the decision within couple of days i.e. not later than 22nd July, 2015.
>>>
>>> 6. Notice Board is yet to be fixed at the lobby entrance. Keys to letter boxes have not been handed over and name plates on it have not been affixed.
>>> D.J. : Both the pending work will be completed by 26th July, 2015.
>>>
>>> 7. Speed breakers within complex are not painted and some flaws were observed in their design, which was cause of minor accidents.
>>> D.J. : He took a look at speed breakers personally and will be updating the steps taken in this regard by 21st July, 2015.
>>>
>>> 8. Garbage disposal should be done more frequently as sometimes it is getting piled up.
>>> D.J. : He will advise the resolution by 20th July, 2015.
>>>
>>> 9. Additional CCTV cameras should be installed to cover entrance of lobby area of both wings of B building.
>>> D.J. : The decision in this regard will be conveyed by 24th July, 2015.
>>>
>>> 10. Many residents complained about video door phone camera positioning and also door bell ring volume issue.
>>> D.J.: Matter will be taken up with concerned vendors and issues will be resolved individually at the earliest.
>>>
>>> 11. The existing temporary gate entrance is a blind turn for vehicles and is prone to accidents. One minor accident was also reported. We have suggested to install a convex mirror in front of the entrance which can resolve the issue to some extent.
>>> D. J. : He has assured to take cognizance of the suggestion and also has agreed to put some temporary barricade which can be operated by a security person.
>>>
>>> 12. Break-up of maintenance fund utilization was requested.
>>> D.J. : It will be given shortly.
>>>
>>>
>>> ON BEHALF OF CASA IMPERIA B WING RESIDENTS.
>>
>>
>
--Regards,Amit SinhaCasa ImperiaS. No 59/62, Near Hinjewadi Bridge ,Jamdade VastiWakadPune -411057Contact No : 9326056222/9326053222/9689934091URL Link : www.casaimperia.in--Regards,Amit SinhaCasa ImperiaS. No 59/62, Near Hinjewadi Bridge ,Jamdade VastiWakadPune -411057Contact No : 9326056222/9326053222/9689934091URL Link : www.casaimperia.in--Vijayshree Patil