Hello All,
I had word with Dhananjay last week. He told that they have sanctioned top floors in this month only and from now work will speed up. He also ask me to visit on Jan end to see actual progress. Also explained that as brick work of top floors not started, they could not finish 1 to 8 floors(?) so they had concentrated on internal work like kitchen, plaster, door frames etc.
I have one more issue about my daughter's admission. I am not sure where should I enroll her for next year as possession date still not clear? Is anybody from us facing problem like this and help me out?
-Jayesh
On Wed, 06 Nov 2013 23:43:36 +0530 wrote
> Dear all,
I too have paid through the mortgage itself.
Regards
Aarti
Sent from my iPad
On Nov 6, 2013, at 9:34 PM, Gaurav dhing wrote:
Hi,
I have paid more than 80% a while back. I think since the builder does not have approval for 9-12 floors yet (didn't know this when i made the payment), he was not supposed to ask for payment corresponding to these floors (which are illlegal so to say) + brick work etc which amounts to 26% of agreement cost.
We should ask builder to pay back additional money - over and above 74% of agreement cost until the approval for higher floors is obtained.
Thanks,
Gaurav.
On Tuesday, November 5, 2013 7:27:41 AM UTC+5:30, Manohar Rao wrote:
Guys,
I would also like to know how much each one of us paid to builder. For me almost 80% of flat cost is already paid. Considering the possession was promised on Dec this was OK, But now since they are moving ahead the possession date this is big loss with respect to overall cost of the flat ( considering the amount I will be paying to Home loan interest till then)
Also we should identify what all we can do collectively to push builder for early possession.
Thanks
Manohar Rao
B1-203
On Tuesday, 22 October 2013 15:35:02 UTC+5:30, Gaurav Khadse wrote:
Dear All,
Just got off the phone with the Casa Imperia Sales Team. They said possession date for B1 & B2 is nowJune 2014. At the time of booking it was supposed to be ath the time of Diwali.
Agreement of flats above 8th floor is expected to start by this month end. They are saying this for quite some time now. At the time of booking in January it was 45 days and still agreement did not happen.
You can call me on
7709690034 in case you are also waiting for agreement or facing any other issue.
Regards,
Gaurav Khadse